ATSSA Traffic Control Supervisor "The Typical Project"
Module 7
Constructability - ANS -Nature of the work
access requirements
drainage issues, drainage during construction
construction equipment
size of work space
Access to work area
room to maneuver equipment
\Daytime work 1 to 12 hours
cones and portable signs - ANS -Short-term stationary (MUTCD work duration category)
\Design - ANS -What stage:
Select best traffic control alternative
based on: safety, mobility, cost, constructability
\Long-term stationary
Intermediate-term stationary
short-term stationary
short-duration
mobile - ANS -What are the MUTCD categories of Work Duration?
\More than 1 day, less than 3 days
Nightime work of more than 1 hour - ANS -Intermediate-stationary (MUTCD work duration category)
\Notify Those affected
Pre-con meeting
Inspection before delivery of devices - ANS -Pre-construction activities
\Occupies location more than 3 days
Module 7
Constructability - ANS -Nature of the work
access requirements
drainage issues, drainage during construction
construction equipment
size of work space
Access to work area
room to maneuver equipment
\Daytime work 1 to 12 hours
cones and portable signs - ANS -Short-term stationary (MUTCD work duration category)
\Design - ANS -What stage:
Select best traffic control alternative
based on: safety, mobility, cost, constructability
\Long-term stationary
Intermediate-term stationary
short-term stationary
short-duration
mobile - ANS -What are the MUTCD categories of Work Duration?
\More than 1 day, less than 3 days
Nightime work of more than 1 hour - ANS -Intermediate-stationary (MUTCD work duration category)
\Notify Those affected
Pre-con meeting
Inspection before delivery of devices - ANS -Pre-construction activities
\Occupies location more than 3 days