AFI 10-245, Antiterrorism - CORRECT ANSWER✅✅✅CE shall: have at least 1 engineer at each base
must complete Security Eng AT Planning & Design Course, review, document, and track construction
projects AT compliance, provide vulnerability assessment protection option program (VAPO) analysis for
all critical facilities and off-base leases, and work with the Base Antiterrorism Officer
Antiterrorism Requirement Planning - CORRECT ANSWER✅✅✅1. UFC 4-020-01
2. Is only the minimum standard required?
3. Yes: construction standoff distance available?
No: UFC 4-020-02 and support manuals
4. If standoff distance is available, apply UFC 4-010-01 and support manuals
Design Basis Threat (DBT) - CORRECT ANSWER✅✅✅Baseline threat used in the design of protective
measures
Initial DBT - CORRECT ANSWER✅✅✅Based on planning team, local intel and Geographic Combatant
Command (COCOM) Theater-Wide threat assessments
Modify Initial DBT - CORRECT ANSWER✅✅✅Local threat assessments
Level of Protection - CORRECT ANSWER✅✅✅The degree to which an asset is protected, defines the
amount of damage a facility or asset can sustain during an attack
LOP: Very low - CORRECT ANSWER✅✅✅Progressive collapse is unlikely, but space in and around
damaged area will be unusable and onset of structural collapse occurs. Glazing is likely to be propelled
into the building and cause serious injuries. Doors may be propelled into rooms, presenting serious
hazards.
LOP: Low - CORRECT ANSWER✅✅✅Building will not be economically repairable and space in and
around damaged area will not be usable, but progressive collapse will not occur. Glazing will fracture
and may come out of the frame, but does not present a significant injury hazard. Doors may fail but
present minimal hazards.
, LOP: Medium - CORRECT ANSWER✅✅✅Minor damage, space in and around damaged area can be
used and will be fully functional after cleanup and repairs. Glazing will fracture but remain in the frame.
Doors may stay in frames but will not be reusable.
LOP: High - CORRECT ANSWER✅✅✅Minimal to no damage with no permanent definitions. Glazing
will not break. Doors will be reusable.
UFC 4-010-01 - CORRECT ANSWER✅✅✅DoD minimum antiterrorism standards for buildings. Intent
is to reduce mass casualties, minimize collateral damage to nearby facilities, and facilitate future
upgrades and increases FPCON.
UFC 4-020-01 - CORRECT ANSWER✅✅✅DoD Security Engineering Facility Planning Manual. Acts as a
starting point for Garrison Antiterrorism and a quantitative risk-based model. Uses scoring model to
evaluate asset value (0-1.0), threat likelihood (0-1.0), and use of minimum AT standards (<0.5). Includes
cost data and helps establish a DBT and required LOP.
AT/FP misconceptions - CORRECT ANSWER✅✅✅1. Bollards, fences, curbs, and barriers are and
adequate substitution for standoff
2. Existing roads must be moved away from existing buildings
3. All building require standoff
Mandatory design standards - CORRECT ANSWER✅✅✅Standard 1: Standoff distance
Standard 6: Progressive collapse
Standard 10: Glazing
Standard 16: Air Intakes
Minimum standoff distance - CORRECT ANSWER✅✅✅Smallest permissible standoff distance for
new and existing construction, regardless of analysis or hardening of the building. Not used for master
planning or programming.