COSC 475 Test 1 vocab Exam 2025 Questions and Answers 100% Pass Activity - A task or process to be accomplished in a set period of time as part of working toward a larger project goal. An Activity can be assigned to a resource(s) and have an associated cost. Activities are ordered with logic links. Actual Cost - The real amount paid or incurred for labor or materials Activity Relationship - An ordered link between 2 activities representing the order of execution.The 4 relationship types are:FS - Finish to StartSS - Start to StartFF - Finish to FinishSF - Start to Finish Approved Change Requests - Documents of approved changes made to the project contract as a whole (cost, schedule, plan). These are first reviewed by all stakeholders before being approved. Arrow Diagraming Method (ADM) - Arrow diagramming method is a network diagramming technique used in Project Management in which activities are represented by arrows. ADM is also known as the activity-on-arrow (AOA) method. Backward Pass (Backward Plan) - Critical path calculation process which having calculated earliest date for activities on the network. Works backwards to find activities latest start and finish dates/float 2COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED Bar Chart - A chart on which activities are represented by Bars. The Bars length is represented by the activity Duration, and is lined-up on an X-axis time scale. Base Line - A set of dates and costs frozen at the start of the project and used as a basis for performance evaluation as the project progresses. Budgeted Cost - The amount planned ahead and placed aside to execute an activity or an entire project from start to finish Change Estimate - An Estimate evaluating a potential change to a project. Often the estimate focuses on Cost, Schedule and Resource cha

Show more Read less
Institution
COSC 475
Course
COSC 475









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
COSC 475
Course
COSC 475

Document information

Uploaded on
April 29, 2025
Number of pages
9
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

COSC 475 Test 1 vocab Exam 2025
Questions and Answers 100% Pass


Activity - ✔✔A task or process to be accomplished in a set period of time as part of
working toward a larger project goal. An Activity can be assigned to a resource(s) and
have an associated cost. Activities are ordered with logic links.

Actual Cost - ✔✔The real amount paid or incurred for labor or materials

Activity Relationship - ✔✔An ordered link between 2 activities representing the order
of execution.The 4 relationship types are:FS - Finish to StartSS - Start to StartFF - Finish
to FinishSF - Start to Finish

Approved Change Requests - ✔✔Documents of approved changes made to the project
contract as a whole (cost, schedule, plan). These are first reviewed by all stakeholders
before being approved.

Arrow Diagraming Method (ADM) - ✔✔Arrow diagramming method is a network
diagramming technique used in Project Management in which activities are represented
by arrows. ADM is also known as the activity-on-arrow (AOA) method.

Backward Pass (Backward Plan) - ✔✔Critical path calculation process which having
calculated earliest date for activities on the network. Works backwards to find activities
latest start and finish dates/float




COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED 1

, Bar Chart - ✔✔A chart on which activities are represented by Bars. The Bars length is
represented by the activity Duration, and is lined-up on an X-axis time scale.

Base Line - ✔✔A set of dates and costs frozen at the start of the project and used as a
basis for performance evaluation as the project progresses.

Budgeted Cost - ✔✔The amount planned ahead and placed aside to execute an activity
or an entire project from start to finish

Change Estimate - ✔✔An Estimate evaluating a potential change to a project. Often the
estimate focuses on Cost, Schedule and Resource changes.

Change Impact - ✔✔The effect of a project change on project cost, schedule and
resourcing.

Committed Cost - ✔✔A cost which has not yet been paid, but an agreement, such as a
purchase order or contract, has been made such that the cost is no longer recoverable.

Cost Breakdown Structure (CBS) - ✔✔A breakdown of the project into cost elements for
cost control planning. A CBS will deconstruct a project into various cost elements or
types such as area, phase, discipline, or materials

Critical Activity - ✔✔An activity that is on the project's critical path.

Critical Path - ✔✔A project's critical path is the sequence of network activities which
add up to the longest overall duration. This determines the shortest time possible to
complete the project

Critical Path Method (CPM) Scheduling - ✔✔A project modeling technique and
algorithm for scheduling a set of project activities. Developed in the late 1950s, CPM
scheduling aims to build a model of a project that contains:

1. A list of all activities required to complete the project (typically categorized within a
work breakdown structure),


COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED 2

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
OliviaWest Teachme2-tutor
View profile
Follow You need to be logged in order to follow users or courses
Sold
109
Member since
1 year
Number of followers
17
Documents
8528
Last sold
1 week ago
Pure Orchid Haven.

All Documents,and package deals offered by seller Olivia West.

2.8

22 reviews

5
6
4
2
3
4
2
1
1
9

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions