100% tevredenheidsgarantie Direct beschikbaar na je betaling Lees online óf als PDF Geen vaste maandelijkse kosten 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

COSC 475 Exam 2 UPDATED Exam Questions and CORRECT Answers

Beoordeling
-
Verkocht
-
Pagina's
6
Cijfer
A+
Geüpload op
27-04-2025
Geschreven in
2024/2025

COSC 475 Exam 2 UPDATED Exam Questions and CORRECT Answers If you are running a company and you have a limited number of labor resources but multiple different projects, would distance between the two projects impact your resource leveling options between the two projects? - CORRECT ANSWER - Yes You are a southern California contractor. You have been awarded two projects: one in downtown Los Angeles and one near the Mojave reservation. Each project needs a bulldozer and a crew of 4 at essentially the same time, each with a duration of about 3 weeks. The bulldozer helps accomplish essentially the first 3 weeks of work onsite. Would you share resources between these two projects when both projects have a fixed hard end date? - CORRECT ANSWER - No

Meer zien Lees minder
Instelling
Cosc
Vak
Cosc









Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
Cosc
Vak
Cosc

Documentinformatie

Geüpload op
27 april 2025
Aantal pagina's
6
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

COSC 475 Exam 2 UPDATED Exam
Questions and CORRECT Answers
If you are running a company and you have a limited number of labor resources but multiple
different projects, would distance between the two projects impact your resource leveling options
between the two projects? - CORRECT ANSWER - Yes


You are a southern California contractor. You have been awarded two projects: one in downtown
Los Angeles and one near the Mojave reservation. Each project needs a bulldozer and a crew of 4
at essentially the same time, each with a duration of about 3 weeks. The bulldozer helps
accomplish essentially the first 3 weeks of work onsite. Would you share resources between
these two projects when both projects have a fixed hard end date? - CORRECT
ANSWER - No


If you build the same project 10 times in a row, same building but different locations, do you
always choose the same material management strategy? - CORRECT ANSWER - No


The leveling of resources looks at the overall fluctuations in day to day resource usage
throughout a project, labor and equipment, and attempts to do what to those fluctuations? -
CORRECT ANSWER - Minimize


When pertaining to labor, hourly workers are hired to perform which of the following? -
CORRECT ANSWER - All of the above


Are resource driven schedules and manpower loaded schedules the same thing? Meaning, are the
schedules both driven by the activities in the same way/manner? - CORRECT ANSWER -
No


Which of the following is not a method used to reduce fluctuations the resource profile when
resource leveling? - CORRECT ANSWER - Fast tracking activities

, The main idea of resource leveling is to increase the efficiency of the project and minimize the
overall costs. Leveling which of the following really does not assist in these cost reduction and
efficiency improvement efforts. - CORRECT ANSWER - Materials


Utilizing extreme theories like the inventory buffer theory, is it economical to have all materials
on-site before starting a project to achieve the lowest cost option project (Cost driven, not
schedule driven)? One clue, when referencing just all material being on-site before construction
starts, is that I would refer to this as "The Dream Project" - CORRECT ANSWER -
Uneconomical


If you are GC and have multiple large subcontractors that have labor resources in many states
and multiple crafts, should you bother to resource load your master schedule? - CORRECT
ANSWER - Yes


The assignment of resources required to complete a given activity, or work item, in the required
amount and timing is known as what? - CORRECT ANSWER - Resource allocation


When dealing with work space and the ever changing nature of the work during the life cycle of
a project, which of the following is not considered a work space consideration for planning and
resource leveling? - CORRECT ANSWER - All of the above should be considered


You are a southern California contractor. You have been awarded two projects: one in downtown
Los Angeles and one near the Mojave reservation. Each project needs a safety manager at
essentially the same time, each for a duration of about 6 weeks. Would you share resources
between these two projects when both projects have a flexible end date? The client on each
project has stated that a safety manager will be on-site each day for at least half the days work
duration when crews are on-site. - CORRECT ANSWER - No


We often talk about the backward pass when looking at schedule logic; is there a similar step that
can be done with resource leveling? - CORRECT ANSWER - Yes


When working with our schedules, we are dealing specifically with crews in our resource
calendar. When utilizing a manpower loaded schedule, as we are for HW6 and the semester

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
MGRADES Stanford University
Bekijk profiel
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
1123
Lid sinds
2 jaar
Aantal volgers
104
Documenten
68962
Laatst verkocht
6 uur geleden
MGRADES (Stanford Top Brains)

Welcome to MGRADES Exams, practices and Study materials Just think of me as the plug you will refer to your friends Me and my team will always make sure you get the best value from the exams markets. I offer the best study and exam materials for a wide range of courses and units. Make your study sessions more efficient and effective. Dive in and discover all you need to excel in your academic journey!

3.8

178 beoordelingen

5
76
4
31
3
47
2
9
1
15

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen