The first step in any major construction job.? - ✔✔ correct answer Clearing and Leveling
Clearing the lot ensure.? - ✔✔ correct answer That the various work crew will be able to perform
their job efficiently
Underground Service Alert.? - ✔✔ correct answer A free service that provides damage prevention
services
What will the underground service alert review.? - ✔✔ correct answer All excavation plans and will
send a crew to mark to mark the location of the underground utilities that are entering the property
The underground service alert most be notified at least? - ✔✔ correct answer At least 2 days but no
earlier than 14 days before the excavation begins
Failing to notify Dig Alert before the excavation is subject to? - ✔✔ correct answer A civil penalty in
the amount not to exceed $10,000
If the underground service alert is not notified due to negligence the penalty will be ? - ✔✔ correct
answer Up to $10,000
If the Underground Service Alert is intentionally not notified the penalty will be ? - ✔✔ correct
answer Up to $50,000
Color code indentifiers "white".? - ✔✔ correct answer Proposed excavation
Color code identifier "Red".? - ✔✔ correct answer Electric power lines, cables, conduit and lighting
cables
Color code identifier "orange"? - ✔✔ correct answer Communication, alarm or signal lines, cables or
conduit
Color code identifier " purple". ? - ✔✔ correct answer Reclaimed water line, irrigation and slurry
lines
,California Contractor's License General
Building (B)
Color code identifier " pink"? - ✔✔ correct answer Temporary survey markings
Color code identifier " yellow"? - ✔✔ correct answer Gas, oil, steam, petroleum or gaseous materials
Color code identifier " blue".? - ✔✔ correct answer Potable water
Color code identifier " green"? - ✔✔ correct answer Sewers and drains
Facilities identifiers? CH - ✔✔ correct answer Chemical
Facilities identifiers? E - ✔✔ correct answer Electrical
Facilities identifiers? FO - ✔✔ correct answer Fiber optic
Facilities identifiers? G - ✔✔ correct answer Gas
Facilities identifiers? LPG - ✔✔ correct answer Liquefied petroleum gas
Facilities identifiers? PP - ✔✔ correct answer Petroleum Products
Facilities identifiers?RR - ✔✔ correct answer Railroad signals
Facilities identifiers? S - ✔✔ correct answer Sewer
Facilities identifiers? SD - ✔✔ correct answer Storm Drain
Facilities identifiers?SS - ✔✔ correct answer Storm Sewer
, California Contractor's License General
Building (B)
Facilities identifiers? SL - ✔✔ correct answer Steer light
Facilities identifiers? STM - ✔✔ correct answer Steam
Facilities identifiers? SP - ✔✔ correct answer Slurry system
Facilities identifiers? TEL - ✔✔ correct answer Telephone
Facilities identifiers? TS - ✔✔ correct answer Traffic signal
Facilities identifiers? TV - ✔✔ correct answer Televisión
Facilities identifiers? W - ✔✔ correct answer Water or reclaimed water purple
Leveling the property will provide? - ✔✔ correct answer A flat even surface for the building
foundation
How is the property leveling done? - ✔✔ correct answer Through excavation and filling or other filler
materials such as rocks and concrete
According to the California Building Code the filling Material must be compacted."? - ✔✔ correct
answer To at least 90%
Why additional fill material is Recomended when when initially adding fill material? - ✔✔ correct
answer To allow for compaction
Soil can be either? - ✔✔ correct answer Granular or cohesive
Soils are generally classified into three types? - ✔✔ correct answer Type A,B and C