Which of the following are true about the Product Owner role? (Choose two.)
A.The Product Owner is one person.
B.The Product Owner is accountable for ordering the Product Backlog.
C.Multiple people can share the Product Owner role on a Scrum Team.
D.The Product Owner role can be played by a committee or a team of people -
(answer)A.The Product Owner is one person.
B.The Product Owner is accountable for ordering the Product Backlog.
Who starts the Daily Scrum?
A.The person coming in last. This encourages people to be on time and helps to
stay within the time-box.
B.Whoever the Development Team decides should start.
C.The person who has the token.
D.The Scrum Master. This ensures that the Development Team has the meeting
and stays within the time-box.
E.The person who last broke the build - (answer)B.Whoever the Development
Team decides should start.
A Scrum Team is only allowed to meet with stakeholders during Sprint Review.
True or False - (answer)True
,2|Page
What does it mean for a Development Team to be cross-functional?
A.The Development Team includes not only developers but also business analysts,
architects, and testers.
B.The Development Team includes cross-skilled individuals who are able to
contribute to do what is necessary to deliver an increment of software.
C.Developers on the Development Team work closely with business analysts,
architects, developers and testers who are not on the team.
D.The Development Team is a virtual team drawing from separate teams of
business analysts, architects, developers and testers. - (answer)B.The
Development Team includes cross-skilled individuals who are able to contribute
to do what is necessary to deliver an increment of software.
The time-box for a Daily Scrum?
A.Two minutes per person.
B.15 minutes.
C.15 minutes for a 4-week sprint. For shorter Sprints it is usually shorter.
D.4 hours. E.The same time of day every day - (answer)B.15 mins
Why is the Daily Scrum held at the same time and same place?
A.The consistency reduces complexity.
B.The place can be named.
C.The Product Owner demands it.
D.Rooms are hard to book, and this lets it be booked in advance. - (answer)A.The
consistency reduces complexity.
,3|Page
A properly functioning Scrum Team will have at least one Release Sprint and may
well have several. True or False - (answer)True
Which statement best describes Scrum?A.
A defined and predictive process that confirms to the principles of Scientific
Management.
B.A complete methodology that defines how to develop software.
C.A cookbook that defines best practices for software development.
D.A framework within which complex products in complex environments are
developed. - (answer)D.A framework within which complex products in complex
environments are developed.
Every Scrum team must have a Product Owner and Scrum Master.
A.True. Outcomes affected by their participation and availability.
B.False. A Product Owner can be replaced by a business analyst in the
Development Team.
C.False. A Scrum Master is only required when asked for by the Development
Team.
D.True. Each must be 100% dedicated to the Scrum Team. - (answer)A.True.
Outcomes affected by their participation and availability.
A properly functioning Scrum Team will have at least one Release Sprint and may
well have several.True or False - (answer)True
, 4|Page
Which statement best describes Scrum?
A. defined and predictive process that confirms to the principles of Scientific
Management.
B. complete methodology that defines how to develop software.
C. cookbook that defines best practices for software development.
D. framework within which complex products in complex environments are
developed - (answer)D. framework within which complex products in complex
environments are developed
Which three purposes does the definition of "Done" serve? (Choose three.)
A.Guide the Development Team on how many Product Backlog items to select for
the Sprint.
B.Create a shared understanding of when work is complete. C.Describe the
purpose, objective, and time-box of each Scrum event.
D.Describe the work that must be done before the Sprint is allowed to
end.E.Increase transparency - (answer)B.Create a shared understanding of when
work is complete.
C.Describe the purpose, objective, and time-box of each Scrum event.
D.Describe the work that must be done before the Sprint is allowed to
end.E.Increase transparency
What is the purpose of a Sprint Review?
A.To take time to judge the validity of the project.