"A project manager is appointed to design and develop a strategy for a government
organization. The project manager recognizes that the project has a limited amount of detailed
information to prepare project estimates. However, several other government organizations
have already successfully adopted the same strategy.
In this scenario, which type of estimating method should the project manager select? -
CORRECT ANSWER Analogous estimation (sufficient historical data available to use
analogous estimation)"
"Before a project evaluation meeting, a key stakeholder complains that the project does not
deliver the expected business benefits. The project manager needs to prepare for the meeting
to effectively address the complaint.
What should the project manager do first? - CORRECT ANSWER Review the project
objectives and success criteria."
"A company has launched a new strategic project. The goal and scope of the project were
loosely defined at the executive committee meeting, and the stakeholders have been
appointed. The project manager needs to hold the kickoff meeting. However, most of the
stakeholders are in different locations and some are on vacation.
What should the project manager do? - CORRECT ANSWER Arrange a virtual team kickoff
meeting with the stakeholders"
"An urban hotel design project has an international, multidisciplinary, and cross-cultural team.
The project manager is in the process of developing the first version of the project management
plan.
What should the project manager do? - CORRECT ANSWER Incorporate cultural
considerations into the project management plan"
"The project manager discovers that a stakeholder provides inaccurate status reports to the
steering committee. Moreover, the stakeholder does not have accurate information on the
project.
What should the project manager do first? - CORRECT ANSWER Schedule a meeting with the
stakeholder to discuss the inaccurate reporting and provide accurate information."
"A project manager is reviewing the project status with the team and identifies that a vendor
resource can be released earlier than planned. The project manager reviews the schedule,
1
, confirms this change, and informs the vendor. The vendor argues that the resource must stay
for a certain period of time.
What should the project manager do? - CORRECT ANSWER Consult the terms and
conditions in the vendor contract"
"Project team A is launching a complex program in collaboration with project teams B, C, and D.
What should be the priority for project team A's project manager during the early stages of the
project? - CORRECT ANSWER Ask project teams A, B, C, and D to identify critical
dependencies, risks, and major milestones"
"A project manager for a new project is tasked with applying agile practices to improve team
performance. Which approach should the project manager take? - CORRECT ANSWER
Ensure team retrospectives are done regularly"
"A project manager observed that a team member is becoming increasingly disengaged from an
ongoing project. What should the project manager do to help ensure participation from this
team member? - CORRECT ANSWER Speak to the team member, understand the problem,
and ask the team member to work on corrective actions."
"A project manager in a quickly growing hybrid organization is becoming increasingly frustrated
at the rapid amount of change in daily operations. Several newer team members have already
left the team or have been promoted to other roles in the organization.
What should the project manager do to ensure the project governance remains stable? -
CORRECT ANSWER Work with leadership to update the organizational process assets
(OPAs)."
"A company used to deliver technical services to customers using external labor. When a new
project manager arrived, the team hired specialized personnel to reduce costs by delivering an
in-house service. Some of the stakeholders are frustrated that the resources are taking too
much time to deliver the service.What should the project manager do to address the concern?
- CORRECT ANSWER Increase stakeholders' understanding of the project approach"
"At the start of a project, the team chose to leverage an agile approach to deliver the project,
using user stories to capture requirements. As part of the organization's control framework, the
internal compliance department will request a copy of the approved requirements document.
What should be done to meet this compliance request? - CORRECT ANSWER A.Review the
project approach with compliance, ensuring they understand how it will meet the control
objective."
2
, "A Scrum team noticed a trend of work spilling over for the last several sprints. The root cause
of this has been identified as the code review task. This bottleneck appears to occur because
the team is dependent on an external expert.
What should the project manager do first? - CORRECT ANSWER Assess the team's capability
and identify the required internal training to remove the bottlenecks."
"A project manager has been asked to manage an existing complex project. Some goals have
already been delivered by the previous project manager. While reviewing the project
management plan, the project manager realizes that one of the key deliverables is missing from
the project goal.
What should the project manager do next to ensure the expected project value is delivered? -
CORRECT ANSWER Confirm the expected deliverables and rebaseline the project"
"A complex, multimillion-dollar, multi-year product development project requiring unique
knowledge is 70% complete. Contract termination is a possibility due to project deliverables
and execution being not acceptable. Despite the strained relationship, the vendor is ready for
rework at no penalty.
What should the project manager do to manage this situation? - CORRECT ANSWER
Facilitate the negotiation of the acceptance criteria between the customer and vendor."
"During project execution, the audit team determined that critical regulatory requirements are
not being met. What should the project manager have done first to avoid this problem? -
CORRECT ANSWER Assessed the internal and external regulatory environments"
"The product owner has asked the project manager and the agile team to demonstrate the
completed functionality to key project stakeholders. The project is in its early days and has only
completed three iterations of functionality. This is the first time the stakeholders will be
exposed to an agile project.
What should the project manager do? - CORRECT ANSWER Set expectations with the
stakeholders regarding what agile is, the approach, and that they will be seeing a small amount
of functionality"
"A project manager is contracted to manage a project for a startup with grants from a foreign
source. Midway into this project, the project manager is informed that there is a government
regulatory requirement that might affect the project because the customer has foreign funding
sources.
3