BAC - correct answer performance baseline cost, what is the project expected to
cost.
PV - correct answer planned value, budgeted cost of work scheduled, value of work
that should be hen completed at given point in time.
AC - correct answer actual cost actual cost of work performed. cost of work that has
been completed at a given point in time.
EV - correct answer budgeted cost of work performance. BAC x % complete
SPI - correct answer schedule performance index
EV/PV
efficiency indicator of planned vs actual
1 or 100 = perfectly efficient
greater than 1 project is ahead of schedule
if less than 1 project is behind schedule or inneficient
SV - correct answer schedule variance
EV-PV
variance indicator of how much ahead or behind schedule
zero means project is on schedule
greater than 0 is ahead of schedule
less than 0 is behind schedule
CPI - correct answer cost performance index
EV/AC