F-60 / Fire Guard for Torch Operations
A transportation permit must be displayed on the ____. - ANS-Vehicle.
\All hot work authorizations must be returned to the ____ upon completion of the
work. - ANS-Responsible person.
\All original hot work authorizations must be filed with ____ hot work permit section. -
ANS-The FDNY.
\All permits shall be readily available on the premises for inspection by who? -
ANS-The FDNY.
\Always approach a fire from an ____ direction, never a ____ direction. -
ANS-Upwind / Downwind
\Always direct the fire extinguisher chemical stream at the ____ of the flame, never
at the center of the flame. - ANS-Base
\An additional F-60 fire guard is required to perform fire watch on the floor ____ if the
torch operation is being conducted in a way that allows sparks and slag to travel
there. - ANS-Below.
\Any single compressed natural gas (CNG) container must not exceed ____
standard cubic feet (SCF). - ANS-381
\Any single liquefied petroleum gas (LPG) container must not exceed ____ lbs in
weight. - ANS-100
\Areas designed for hot work operations shall have floors with ____ surfaces. -
ANS-Non-combustible.
\At a construction site and torch-applied roofing system operation, every torch
operator must have ____. - ANS-An F-60 COF holder performing a fire watch, unless
the 2nd torch operation is not more than 50 feet away from the fire guard.
\At least one portable fire extinguisher with a minimum 2-A:20-B:C rating must be
accessible within ____ feet of the location where hot work is performed. - ANS-30
\Before hot work is authorized and at least ____ per day, the hot work area shall be
inspected for safety by the responsible person. - ANS-Once.
\Fire watch for impairment must be provided when the alarm system is ____. -
ANS-Off-line.
\For a piped gas leak fire, never attempt to extinguish the flames unless the gas
supply has been ____. - ANS-Shut off.
\For all hot work operations, the premises owner must designate a ____. -
ANS-Responsible person.
\For any CNG or LPG torch operation, two inspections must be conducted after
completion of the work. When must each inspection be conducted? - ANS-The first,
30 minutes after. The second, 1 hour after.
\For hot work operations with a citywide permit, the premises owner must be notified
in writing by the permit holder at least ____ hours before hot work begins. - ANS-48
A transportation permit must be displayed on the ____. - ANS-Vehicle.
\All hot work authorizations must be returned to the ____ upon completion of the
work. - ANS-Responsible person.
\All original hot work authorizations must be filed with ____ hot work permit section. -
ANS-The FDNY.
\All permits shall be readily available on the premises for inspection by who? -
ANS-The FDNY.
\Always approach a fire from an ____ direction, never a ____ direction. -
ANS-Upwind / Downwind
\Always direct the fire extinguisher chemical stream at the ____ of the flame, never
at the center of the flame. - ANS-Base
\An additional F-60 fire guard is required to perform fire watch on the floor ____ if the
torch operation is being conducted in a way that allows sparks and slag to travel
there. - ANS-Below.
\Any single compressed natural gas (CNG) container must not exceed ____
standard cubic feet (SCF). - ANS-381
\Any single liquefied petroleum gas (LPG) container must not exceed ____ lbs in
weight. - ANS-100
\Areas designed for hot work operations shall have floors with ____ surfaces. -
ANS-Non-combustible.
\At a construction site and torch-applied roofing system operation, every torch
operator must have ____. - ANS-An F-60 COF holder performing a fire watch, unless
the 2nd torch operation is not more than 50 feet away from the fire guard.
\At least one portable fire extinguisher with a minimum 2-A:20-B:C rating must be
accessible within ____ feet of the location where hot work is performed. - ANS-30
\Before hot work is authorized and at least ____ per day, the hot work area shall be
inspected for safety by the responsible person. - ANS-Once.
\Fire watch for impairment must be provided when the alarm system is ____. -
ANS-Off-line.
\For a piped gas leak fire, never attempt to extinguish the flames unless the gas
supply has been ____. - ANS-Shut off.
\For all hot work operations, the premises owner must designate a ____. -
ANS-Responsible person.
\For any CNG or LPG torch operation, two inspections must be conducted after
completion of the work. When must each inspection be conducted? - ANS-The first,
30 minutes after. The second, 1 hour after.
\For hot work operations with a citywide permit, the premises owner must be notified
in writing by the permit holder at least ____ hours before hot work begins. - ANS-48