and Answers 100% Pass
Is the most traditional project delivery method and appeals to those
looking for low-cost bids. In this method, the owner contracts designers
and builders separately. - ✔✔Design-bid-build
is a construction project delivery method where the designer and builder
work together under a single contract from the beginning of the project in
order to ensure unity and collaboration throughout the process. -
✔✔Design- build
Select all that clearly demonstrate an advantage of the Design-Build project
delivery over the Design-Bid-Build approach:
- There is single point of contractual responsibility for the owner for the
entire project
1
Katelyn Whitman, All Rights Reserved © 2025
,-There are contractual relationships with the Owner that prevent a conflict
of interest
-The design is clearly and explicitly defined at the outset of the project
- The design includes significant collaboration between the Engineer and
the Contractor
-The schedule can be fast-tracked and construction can begin before the
complete project design is finalized
- The Owner will receive a project at the lowest competitive cost - ✔✔There
is single point of contractual responsibility for the owner for the entire
project
There is single point of contractual responsibility for the owner for the
entire project
The schedule can be fast-tracked and construction can begin before the
complete project design is finalized
2
Katelyn Whitman, All Rights Reserved © 2025
,An indemnification clause in an engineer's design contract is typically tied
to:
A. Negligent engineering design
B. Claims submitted by parties affected by a failure
C. Project cost overruns
D. Improper construction methods by the Contractor - ✔✔A. Negligent
engineering design
Collusion on a construction project typically refers to which of the
following?
A. A practice where multiple contractors conspire to fix prices or rig bids
B. A system where public officials receive money from the contractor after
award
C. Falsely increasing the price of change order
3
Katelyn Whitman, All Rights Reserved © 2025
, D. Misrepresenting the amount of work that has been completed to get
advance payments - ✔✔A. A practice where multiple contractors conspire
to fix prices or rig bids
A preconstruction conference should be he held:
A. Prior to advertising for bids
B. After advertising for bids but before bids are received
C. After bid opening but before award of the contract
D. After execution of an agreement but before Notice to Proceed - ✔✔D.
After execution of an agreement but before Notice to Proceed
Types of submittals for engineer approval typically include all the
following except:
A. Product data
B. Shop drawings
C. Installation means and methods
4