100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4.2 TrustPilot
logo-home
Examen

CONSTRUCTION FE CIVIL UPDATED EXAM WITH MOST TESTED QUESTIONS AND ANSWERS | GRADED A+ | ASSURED SUCCESS WITH DETAILED RATIONALES

Puntuación
-
Vendido
-
Páginas
31
Grado
A
Subido en
10-03-2025
Escrito en
2024/2025

CONSTRUCTION FE CIVIL UPDATED EXAM WITH MOST TESTED QUESTIONS AND ANSWERS | GRADED A+ | ASSURED SUCCESS WITH DETAILED RATIONALES

Institución
CONSTRUCTION FE CIVIL
Grado
CONSTRUCTION FE CIVIL











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
CONSTRUCTION FE CIVIL
Grado
CONSTRUCTION FE CIVIL

Información del documento

Subido en
10 de marzo de 2025
Número de páginas
31
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

ESTUDY



CONSTRUCTION FE CIVIL UPDATED EXAM WITH MOST
TESTED QUESTIONS AND ANSWERS | GRADED A+ |
ASSURED SUCCESS WITH DETAILED RATIONALES

1. **Which project delivery method is the most traditional and appeals to those looking for low-cost
bids, where the owner contracts designers and builders separately?**



- A) Design-Bid-Build

- B) Design-Build

- C) Construction Management at Risk

- D) Integrated Project Delivery



**Answer: A) Design-Bid-Build**



2. **Which construction project delivery method involves the designer and builder working together
under a single contract from the beginning to ensure unity and collaboration throughout the project?**



- A) Design-Bid-Build

- B) Design-Build

- C) Construction Management at Risk

- D) Integrated Project Delivery



**Answer: B) Design-Build**



3. **Which of the following clearly shows an advantage of the Design-Build project delivery over the
Design-Bid-Build method?**

,ESTUDY




- A) There is a single point of contractual responsibility for the owner for the entire project

- B) There are contractual relationships with the Owner that prevent a conflict of interest

- C) The design is clearly and explicitly defined at the outset of the project

- D) The design includes significant collaboration between the Engineer and the Contractor

- E) The schedule can be fast-tracked and construction can begin before the complete project design is
finalized

- F) The Owner will receive a project at the lowest competitive cost



**Answer: A) There is a single point of contractual responsibility for the owner for the entire project**



4. **What is an indemnification clause in an engineer's design contract typically tied to?**



- A) Negligent engineering design

- B) Claims submitted by parties affected by a failure

- C) Project cost overruns

- D) Improper construction methods by the Contractor



**Answer: A) Negligent engineering design**



5. **What does "collusion" on a construction project typically refer to?**



- A) A practice where multiple contractors conspire to fix prices or rig bids

- B) A system where public officials receive money from the contractor after award

- C) Falsely increasing the price of change orders

- D) Misrepresenting the amount of work completed to get advance payments

,ESTUDY




**Answer: A) A practice where multiple contractors conspire to fix prices or rig bids**



6. **When should a preconstruction conference be held?**



- A) Prior to advertising for bids

- B) After advertising for bids but before bids are received

- C) After bid opening but before the contract is awarded

- D) After execution of an agreement but before the Notice to Proceed



**Answer: D) After execution of an agreement but before Notice to Proceed**



7. **Which of the following types of submittals for engineer approval is NOT typically required?**



- A) Product data

- B) Shop drawings

- C) Installation means and methods

- D) Mill certificates



**Answer: C) Installation means and methods**



8. **What does "substantial completion" mean in a construction contract?**



- A) The project is completely finished and can be used by the owner

- B) The project can be used and occupied by the owner, but there is still minor work left

, ESTUDY


- C) The contractor's performance bond will be used to finish the remaining work

- D) The owner has received a final release of liens from all subcontractors



**Answer: B) The project can be used and occupied by the owner, but there is still a punch-list of
minor work remaining**



9. **What is a financial guarantee that the terms of a contract will be honored, and if a party cannot
fulfill their obligations, the bond compensates the other party?**



- A) Performance bond

- B) Insurance bond

- C) Payment bond

- D) Completion bond



**Answer: A) Performance bond**



10. **OSHA requires trench protection systems to be installed for the safety of workers when:**



- A) Whenever a trench is dug and workers will be working in it

- B) For trenches 5 feet deep or greater unless the trench is made entirely in stable rock

- C) When the work in the trench will exceed four hours

- D) Only if the trench is 8 feet deep or greater or 20 feet long or greater



**Answer: B) For trenches 5 feet deep or greater unless the trench is made entirely in stable rock**



11. **Who is primarily responsible for planning the means and methods of construction?**
$15.49
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Estudyr Kaplan University
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
1155
Miembro desde
3 año
Número de seguidores
828
Documentos
10861
Última venta
19 horas hace
ESTUDY

Get best related and owned assignment help online, this is your youngest Proffesor around.Be Smart! , I will be sharing all materials, Nclex, study guides, tests, Question ,Answers and Rationales , test banks, Hesi questions, etc. on my page for , All are based on my experiences with Nursing school.| Feel free to message me with any questions, happy to help!

3.9

207 reseñas

5
103
4
43
3
27
2
11
1
23

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes