DAU - PM Practitioner Test Questions Solved Correctly Latest Version A software-costing model that bases cost estimates upon statistical data such as source lines of code is an example of a ________costing model - Answers Parametric As a general rule of thumb, what percent of the total ownership costs of a mass-produced system occur late in the life cycle, due to costs associated with operations and support? - Answers 65-80% Below Threshold reprogramming is approved by who? - Answers Individual services and defense agencies Affordability is most concerned with: - Answers Making tradeoffs in performance and schedule to achieve cost objectives within affordability constraints. Escalation allows us to make predictions about future costs based on: - Answers Expected inflation and outlay rates When both government and private funds are used in development efforts, the contractor may be entitled to offer rights that allow the government to release data only as part of the competition and not for commercial purposes are called _______________ rights? - Answers Government Purpose With respect to product improvements, if a modification will not cause an increase in system performance, does not require extensive independent testing, and the system is currently in production, its development and test as well as modification kits should be funded with __________ dollars. - Answers Procurement Forward Pricing Rates Agreements (FPRA) provide negotiated rates that represent reasonable projections for such things as _______________________. - Answers Rates for labor and indirect costs Who controls the budget and the release of funds, and reports directly to the Secretary of Defense? - Answers Under Secretary of Defense Comptroller (OUSD(C)) The primary unit of data in the Future Years Defense Program (FYDP) and normally the smallest aggregation of resources controlled by the office of the Secretary of Defense (OSD) is the ____________. - Answers Program Element Which process of DoD Resource Allocation, does Congress appoint various budget, authorization, and appropriation committees to set the budget ceiling and ends when the President signs the National Defense Authorization Act (NDAA)? - Answers Enactment What is the obligation period (the length of time the Government has to obligate the funds) for the Defense Appropriation Category of Procurement funds? - Answers 3 Years Which enactment process activity provides permission for a Federal program or activity to begin or continue from year to year, but does not provide Budget Authority to fund the program or activity? - Answers Authorization Bill After Congress passes the DoD Appropriations Bill and the President signs it, the Office of Management and Budget (OMB) distributes the Budget Authority to the DoD. What is this distribution called? - Answers Apportionment If a contractor is producing missiles for the Navy, on a non-commercial contract, and the contractor fails to deliver them on time, the Navy has the right to: - Answers Terminate the contract for default If your procurement budget request did not provide for buying a whole number of useable end items, this would be a violation of which funding policy? - Answers Full Funding The largest percentage of software life cycle costs is associated with what? - Answers Upgrades and Maintenance When a vendor cashes the government check and money flows from the Treasury to the vendor it is called an ______________. - Answers Outlay Which of the following institutions issues directives and regulations and formulates, directs, and executes national security policy? - Answers The Executive Branch If a Program Manager's current estimate indicates a potential breach of the Acquisition Program Baseline (APB) the Milestone Decision Authority (MDA) should be notified ______________________. - Answers Immediately In order to be successful in acquisition management, which of the following SCHEDULE risk factors must be assessed. - Answers Late deliveries Which opportunity management option includes intentionally ignoring an opportunity because of cost, technical readiness, resources, schedule burden, and/or low probability of successful capture? - Answers Reject The Defense Security Cooperation Agency asks a Military Department to engage their acquisition counterparts in allied and friendly nations regarding the potential benefits of acquiring an upgraded U.S. system that could provide additional coalition capability in the region in order to bolster the U.S. influence in the region. This initiative supports the achievement of which DoD Security Cooperation objective? - Answers Equipment Sales and Financing Which of the following did the adoption of Joint Capabilities Integration and Development System (JCIDS) allow DoD to do? - Answers Shift from a threat-based approach to identifying warfighter requirements to a capabilities-based approach Which of the following is NOT conducted during the Production and Deployment (P&D) Phase? - Answers Development Request for Proposal Release Decision (DRFPRD)

Show more Read less
Institution
DAU - PM
Module
DAU - PM









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
DAU - PM
Module
DAU - PM

Document information

Uploaded on
March 7, 2025
Number of pages
10
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

DAU - PM Practitioner Test Questions Solved Correctly Latest Version 2025-2026

A software-costing model that bases cost estimates upon statistical data such as source lines of code is
an example of a ________costing model - Answers Parametric

As a general rule of thumb, what percent of the total ownership costs of a mass-produced system occur
late in the life cycle, due to costs associated with operations and support? - Answers 65-80%

Below Threshold reprogramming is approved by who? - Answers Individual services and defense
agencies

Affordability is most concerned with: - Answers Making tradeoffs in performance and schedule to
achieve cost objectives within affordability constraints.

Escalation allows us to make predictions about future costs based on: - Answers Expected inflation and
outlay rates

When both government and private funds are used in development efforts, the contractor may be
entitled to offer rights that allow the government to release data only as part of the competition and not
for commercial purposes are called _______________ rights? - Answers Government Purpose

With respect to product improvements, if a modification will not cause an increase in system
performance, does not require extensive independent testing, and the system is currently in production,
its development and test as well as modification kits should be funded with __________ dollars. -
Answers Procurement

Forward Pricing Rates Agreements (FPRA) provide negotiated rates that represent reasonable
projections for such things as _______________________. - Answers Rates for labor and indirect costs

Who controls the budget and the release of funds, and reports directly to the Secretary of Defense? -
Answers Under Secretary of Defense Comptroller (OUSD(C))

The primary unit of data in the Future Years Defense Program (FYDP) and normally the smallest
aggregation of resources controlled by the office of the Secretary of Defense (OSD) is the ____________.
- Answers Program Element

Which process of DoD Resource Allocation, does Congress appoint various budget, authorization, and
appropriation committees to set the budget ceiling and ends when the President signs the National
Defense Authorization Act (NDAA)? - Answers Enactment

What is the obligation period (the length of time the Government has to obligate the funds) for the
Defense Appropriation Category of Procurement funds? - Answers 3 Years

Which enactment process activity provides permission for a Federal program or activity to begin or
continue from year to year, but does not provide Budget Authority to fund the program or activity? -
Answers Authorization Bill

, After Congress passes the DoD Appropriations Bill and the President signs it, the Office of Management
and Budget (OMB) distributes the Budget Authority to the DoD. What is this distribution called? -
Answers Apportionment

If a contractor is producing missiles for the Navy, on a non-commercial contract, and the contractor fails
to deliver them on time, the Navy has the right to: - Answers Terminate the contract for default

If your procurement budget request did not provide for buying a whole number of useable end items,
this would be a violation of which funding policy? - Answers Full Funding

The largest percentage of software life cycle costs is associated with what? - Answers Upgrades and
Maintenance

When a vendor cashes the government check and money flows from the Treasury to the vendor it is
called an ______________. - Answers Outlay

Which of the following institutions issues directives and regulations and formulates, directs, and
executes national security policy? - Answers The Executive Branch

If a Program Manager's current estimate indicates a potential breach of the Acquisition Program
Baseline (APB) the Milestone Decision Authority (MDA) should be notified ______________________. -
Answers Immediately

In order to be successful in acquisition management, which of the following SCHEDULE risk factors must
be assessed. - Answers Late deliveries

Which opportunity management option includes intentionally ignoring an opportunity because of cost,
technical readiness, resources, schedule burden, and/or low probability of successful capture? - Answers
Reject

The Defense Security Cooperation Agency asks a Military Department to engage their acquisition
counterparts in allied and friendly nations regarding the potential benefits of acquiring an upgraded U.S.
system that could provide additional coalition capability in the region in order to bolster the U.S.
influence in the region. This initiative supports the achievement of which DoD Security Cooperation
objective? - Answers Equipment Sales and Financing

Which of the following did the adoption of Joint Capabilities Integration and Development System
(JCIDS) allow DoD to do? - Answers Shift from a threat-based approach to identifying warfighter
requirements to a capabilities-based approach

Which of the following is NOT conducted during the Production and Deployment (P&D) Phase? -
Answers Development Request for Proposal Release Decision (DRFPRD)

The DoD Adaptive Acquisition Framework (AAF) supports the Defense Acquisition System (DAS) with the
objective of delivering _____________, suitable, survivable, sustainable, and affordable solutions to the
end user in a timely manner. - Answers Effective

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TutorJosh Chamberlain College Of Nursing
View profile
Follow You need to be logged in order to follow users or courses
Sold
343
Member since
1 year
Number of followers
16
Documents
28821
Last sold
3 days ago
Tutor Joshua

Here You will find all Documents and Package Deals Offered By Tutor Joshua.

3.6

53 reviews

5
18
4
14
3
12
2
0
1
9

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions