CDS - EXAM 1 QUESTIONS AND ANSWERS
Labor and material payment bonds provide the necessary protection on public projects -
Correct Answer- TRUE

Miller act corresponds with what.? - Correct Answer- Labor and material payment bond

Architects should not advise owners and the legal sufficiency of required affidavits,
waivers, or releases of liens. - Correct Answer- TRUE

Liens are not permitted on public projects. - Correct Answer- TRUE

Architect must review, approve, and promptly submit shop drawings required by the
contract documents. - Correct Answer- TRUE

An architect approved shop drawings which deviated from the contract documents. -
Correct Answer- Changes in contract drawings must be submitted in writing to architect
before becoming affective, not equal to revisions within shop drawings.

Who is responsible for errors and omissions in shop drawings? - Correct Answer-
General Contractor

Revisions not requested by the architect on resubmitted shop drawings don't require
architect's approval? - Correct Answer- FALSE

A contractors stamp of approval on shop drawings means that the contractor has
already determined all criteria related thereto. - Correct Answer- FALSE

AIA document B101 is used to outline the architects service obligations? - Correct
Answer- TRUE

The architects responsibilities are re-stated within the AIA General Conditions Doc
A201. - Correct Answer- TRUE

Contractors may not know what services the architect is obligated to perform if what
document is not part of the contract documents. - Correct Answer- AIA Document B101

In review of shop drawings the general conditions Document A201 clearly states? -
Correct Answer- Matters outside the scope of the design concept and the contract
documents are not reviewed.

, If an architect had performed their services using stipulations of AIA documents A201 &
B141 within a ______ there should be no concern about professional liability. But
general liability is different. - Correct Answer- Standard of care

Calendar days - Correct Answer- 7 / Week

Liquidated damages is a provision included in the? - Correct Answer- Owner-contractor
agreement. Document A101.

An amount of money stipulated in the contract that is chargeable against the contractor
is reimbursement for damages suffered by the owner because the contractors failure to
fulfill his or her contractual obligation's. - Correct Answer- Liquidated damages

What clause should be used when a slight delay in schedule can cause a breach of
contract? - Correct Answer- Time is of the essence

CPM is superior to a Bar Chart because it shows durations, sequences and
relationships to other activities. - Correct Answer- TRUE

And small projects what type of progress schedule should be used? - Correct Answer-
Bar chart

And larger complex projects what type of progress schedule should be used? - Correct
Answer- Critical path method CPM

How many days the contractor have to notify the architect in conditions of force
majeure? - Correct Answer- 21 days

Time extensions caused by the owner automatically entitle the contractor to monetary
damages? - Correct Answer- FALSE

Standard AIA documents provided means by which the contractor may make a claim for
time extensions, monetary damages, or both. - Correct Answer- TRUE

General requirements are often used to detail provisions related to scheduling and the
consequences of delays. - Correct Answer- FALSE

What is required prior to the contractor submitting the first application for payment? -
Correct Answer- Schedule of values

Document information

Uploaded on
March 5, 2025
Number of pages
9
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$32.58

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
4
Followers
0
Items
10
Last sold
11 months ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions