Team B is discussing new functionality when it becomes clear that two developers
have different ideas on how to implement the Solution. Which of the following
characteristics of a high-performing team an help Team B continue a productive
discussion and arrive at a shared plan? - correct answer✔️✔️Healthy conflict
What is one purpose of acceptance criteria? - correct answer✔️✔️To identify how
the Story can be validated
According to SAFe, what is one common characteristic of effective Scrum
Masters/Team Coaches? - correct answer✔️✔️Conflict Navigator
According to SAFe, what is method Scrum Masters/Team coaches should use to
visualize team delivery? - correct answer✔️✔️Burn-up chart
According to SAFe, what is one approach to retrospectives? - correct
answer✔️✔E ️ nsure the event ends with actionable improvement items for the
backlog
What is one element of the CALMR approach to DevOps? - correct
answer✔️✔️Create a culture of shared responsibility
What is one anti-pattern that indicates a team is overcommitting to work?
Team velocity increases over time
Capacity and load are exactly the same - correct answer✔️✔️Capacity and load
are exactly the same?
1
, STUDYSAGE
Team A has decided to use the IP Iteration to continue the finalizing Feature
delivery work they have been working on for the past two IP Iterations. What is
one effect Team A might experience by continuing to stay heads-down rather that
using the IP Iteration as intended? - correct answer✔️✔️They could lose an
opportunity to consider new approaches to Solution delivery
What is one organizing attribute that teams share with the other teams on their
ART? - correct answer✔️✔️Synchronization to a common cadence
During which of the following events can Scrum Masters/Team Coach escalate
ART-level impediments? - correct answer✔️✔️Coach Sync
What are the three pats of an Inspect and Adapt event? - correct answer✔️✔️PI
system Demo, Qualitative and quantitative measurement, and problem-solving
workshop
What is one question a Scrum Master/Team Coach must answer during PI
Planning Coach Sync? - correct answer✔️✔️Have you identified an ART risks?
What is a common anti-pattern for teams trying to prepare their draft objectives at
PI Planning? - correct answer✔️✔️Too much time is spent analyzing each Story
What is one example of effective Scrum Masters/Team Coaches thinking beyond
the day-to-day? - correct answer✔️✔️Help the team prioritize improvement
activities to ensure progress
Which of the following statements describes a servant leader? - correct
answer✔️✔️A leader that prioritizes the needs and growth of the team over their
own priorities