CS302 TEST REVIEW QUESTIONS
AND ANSWERS
Who is responsible for approving the Project Management Plan?
A. Project manager and stakeholders
B. Project manager and sponsor
C. Project manager, sponsor and key stakeholders
D. Sponsor only - ANSWER Project manager, sponsor and key stakeholders
::The Project Management Plan is the master plan from which the project will
be executed. It is the responsibility of all parties (project manager, sponsor, and
key stakeholders) to approve the Project Management Plan.
You are analyzing quality results looking for a relationship between defects and
their causes. Which of the following is the appropriate tool
A. Tornado diagram
B. Ishikawa diagram
C. Control chart
D. Histogram - ANSWER B. Ishikawa diagram
::The question is describing cause and effect analysis, for which you would use
an Ishikawa diagram (fishbone)
What is the purpose of a RACI matrix?
A. Displays the relationship between work packages and team members
B. Defines communication channels
C. Authorizes work to begin
D. Speeds up the project schedule
Planning - Human Resources Management - ANSWER A. Displays the
relationship between work packages and team members
, ::purpose of a RACI matrix is to show the relationship between work packages
(or activities) and team members.
Your change control board (CCB) has just approved a change request. What is
the next thing you should do?
A. Analyze the impact of the change
B. Inform stakeholders of the change approval
C. Update the project plan to reflect the change
D. Manage the project based on the approved change - ANSWER C. Update
the project plan to reflect the change
::The first thing you should do after a change request is approved is update the
project documents. Once the documents are updated, then you can inform the
stakeholders.
Moreover, some environmental studies suggest that the subsurface in some
areas may be inadequate to sustain the road, which may result in expensive
detours being built around those spots. You are working on your Risk
Management Plan. What is the best way to proceed?
A. Set aside reserves to cover the costs of these risks and others that have been
identified
B. Document each category of risk in the Risk Management Plan to help ensure
all risks are properly identified - ANSWER B. Document each category of risk
in the Risk Management Plan to help ensure all risks are properly identified
::The Risk Management Plan should contain risk categories, which will help
you systematically identify risks as you move through risk planning.
Which of the following does not contain any information about the project
requirements or the characteristics of the product?
A. Requirements documentation
B. Project charter
C. Requirements management plan
D. Project statement of work
AND ANSWERS
Who is responsible for approving the Project Management Plan?
A. Project manager and stakeholders
B. Project manager and sponsor
C. Project manager, sponsor and key stakeholders
D. Sponsor only - ANSWER Project manager, sponsor and key stakeholders
::The Project Management Plan is the master plan from which the project will
be executed. It is the responsibility of all parties (project manager, sponsor, and
key stakeholders) to approve the Project Management Plan.
You are analyzing quality results looking for a relationship between defects and
their causes. Which of the following is the appropriate tool
A. Tornado diagram
B. Ishikawa diagram
C. Control chart
D. Histogram - ANSWER B. Ishikawa diagram
::The question is describing cause and effect analysis, for which you would use
an Ishikawa diagram (fishbone)
What is the purpose of a RACI matrix?
A. Displays the relationship between work packages and team members
B. Defines communication channels
C. Authorizes work to begin
D. Speeds up the project schedule
Planning - Human Resources Management - ANSWER A. Displays the
relationship between work packages and team members
, ::purpose of a RACI matrix is to show the relationship between work packages
(or activities) and team members.
Your change control board (CCB) has just approved a change request. What is
the next thing you should do?
A. Analyze the impact of the change
B. Inform stakeholders of the change approval
C. Update the project plan to reflect the change
D. Manage the project based on the approved change - ANSWER C. Update
the project plan to reflect the change
::The first thing you should do after a change request is approved is update the
project documents. Once the documents are updated, then you can inform the
stakeholders.
Moreover, some environmental studies suggest that the subsurface in some
areas may be inadequate to sustain the road, which may result in expensive
detours being built around those spots. You are working on your Risk
Management Plan. What is the best way to proceed?
A. Set aside reserves to cover the costs of these risks and others that have been
identified
B. Document each category of risk in the Risk Management Plan to help ensure
all risks are properly identified - ANSWER B. Document each category of risk
in the Risk Management Plan to help ensure all risks are properly identified
::The Risk Management Plan should contain risk categories, which will help
you systematically identify risks as you move through risk planning.
Which of the following does not contain any information about the project
requirements or the characteristics of the product?
A. Requirements documentation
B. Project charter
C. Requirements management plan
D. Project statement of work