TEST QUESTIONS AND CORRECT DETAILED ANSWERS
(100% CORRECT VERIFIED SOLUTIONS) LATEST UPDATED
VERSION |ALREADY GRADED A+ (BRAND NEW!!) CQM –C
EXAM
What is a purpose of the coordination and mutual
understanding and meeting (Navy)?
Answer- To review the QC Plan with the contractor.
Which of the following is included in all three phases of
the Three Phases of Control?
Answer- Safety.
The purpose of Construction Quality Management is to:
Answer- Achieve the quality established by properly
developed requirements through the combined
responsibility, but separate efforts of contractor sad
government personnel.
, Construction Quality Management is the performance of
tasks, which ensure that construction is performed.
Answer- According to plans and specifications, on time,
within a defined budget and a safe work environment.
Partnering relationships are based upon:
Answer- Building trust and dedication to common goals
It is the responsibility of Quality Assurance Personnel to:
Answer- Periodically verify that the contractor’s system
of control is working effectively.
An effective contractor quality control program will:
Answer- Be an incentive for work to be done correctly the
first time resulting in earlier completion, reduced field
overhead costs, and greater profits.