CDFM Module 4 Exam Questions and Answers Latest Update 2025 Already Passed What are Joint Acquisition Programs? - Answers Joint Acquisition Programs is any acqusition system, subsystem, component, or technology program with astrategy that includes funding by more than one DoD component during any phase of a system's life cycle. Who decides to place programs under joint acquisition management? - Answers The MDA decides whether to place programs under joint management and designates the lead executive DoD component. What law requires an analysis of potential opportunities of international cooperation? - Answers 10 USC 2350a(e) requires international cooperation consideration in the initial aquisition strategy for a program. When international programs may be established in the defense acqusition program - Answers Decision to include international partners needs to be included during development of the initial capabilities document but no early than the material and solution analysis phase. When is Earned Value Management (EVM) implemented - Answers EVM is part of program management . It ensures that cost , schedule and technical aspects of the contract are truly integrated. In what type of contracts EVM is required - Answers EVM is required on Cost, and/or Incentive contracts valued at greater than $20M. What is EVM? - Answers Earned Value Management is a tool that 1. Relates the scope of the work to its associated budgets and schedule. 2. Measures the work progress in objective terms 3. States that value of the work completed in dollars and other measurable units. What are EVM techniques? - Answers Correlate the budgeted cost of worked scheduled with the budget cost of work performed (BCWP) 1. 0/100 Earned Value Technique 2. Percent Start/Percent Finish EV Technique (50/50) (25/75) (80/20) 3. Percent Complete 4. Units Completed 5. Equivalent Units Describe the Percent Start/Percent Finish EV Technique - Answers Is an objective earned value technique tied to the start and completion of a work package task, often referred to % assigned to the start and finish milestone such as (50/50...) Thsi technique tends to overstate performance in the first half of the period of performance and uderstate performance in the last half. What is the most important step in EVM system? - Answers Is the establishment of the Performance Measurement Baseline (PMB)or the Budgeted Cost of Work Schedule (BCWS) What is the PMB in and EVM? - Answers The PMB includes the undistributed budget, all summary level planning package budgets, and all control account budgets. It does not include management reserve. What is the final step of the PMB? - Answers Is to classify work, to allocate the budget and to time phase the control account work package budgets. This last phase is calculate BWCS How do we classify work packages in EVM? - Answers in 3 categories, Discrete, apportioned effort, and level of effort. Describe the realignment of the PMB - Answers Rebaselining, Replanning, and Reprogramming What is Reprogramming? - Answers Reprogramming is a comprehensive realignment of the remaining performance measurement baseline that results in a total budget and/or total schedule that exceeds the contractual requirements. It is the process that results in an Over-Target Baseline or OTB and an Over-Target Schedule OTS. Schedule Performance Index (SPI) formula - Answers SPI=BCWP/BCWS Estimate at Completion (EAC) formula - Answers EAC=ACWP+[(BAC-BCWP)/(Performance Factor)] EAC Compsite formula - Answers ACWPcum+[(BAC-BCWPcum)/(CPIcum*SPIcum)] Upper Value (worst case) EVM Terminology - Answers EAC=Estimate at Completion BAC=Budget at Completion(current) BCWS=Budget Cost of Work Scheduled (current) BWCP=Budget Cost of Work Performed (earned value) ACWP=Actual Cost of Work Performed What is the Contractor Cost and Software Data Reporting (CSDR) - Answers The CSDR system involves two formal contractor reports, the COntractor Cost Data Report (CCDR) and the Software Resources Data Report (SRDR) What is Contract Performance Report (CPR) - Answers The PM should obtain from the contractor a CPR (DD form 2734) on all contracts the meet or exceed EVMS dollar thresholds and require EVMS compliance. The CPR provides contract cost and schedule performance for program mangement. What is Contract Funds Status Report (CFSR) - Answers (DD 1586) has no specific application thresholds but PMs should evaluate contracts of less than $1.3M. FFP contracts should not apply the CFSR unless unusual circumnstances dictate funding visibility. What is Government Contract Quality Assurance (GCQA) - Answers DCMA Q&A personnel conducts quality assurance as identified in contract administration delegations by the KO. What is Independent Management Reviews (Peer Reviews) - Answers The Director, DPAP organizes review teams and facilitate pre-award and post-award peer reviews for all service contracts with a value of $1B or more (including options) What are Milestone Decision Points? - Answers Milestione Decision Points initiate programs and auhtorize entry into major acquisition process phases MDP B - Answers A favorable decision formally initiates an acquisition program Where are Technology Readiness Assessments reviewed? - Answers At Milestone B & C Milestone Decision Point C - Answers A succesfull outcome at MDP C, results in the program moving into Production and deployment phase At what MDP, if necessary, are Independent technology Readiness Assesments done? - Answers At MDP B&C What are the 4 major reviews? - Answers Materiel Development Decision Review Preliminary Decision Review Critical Design Review Full Rate Production Decision Review What is the role fo USD (AT&L) - Answers AT&L is the Defense Acqusition Executive (DAE) and conducts Defense Acquisition Board reviews for acquisition category ID programs at major program milestones. Who advises USD (AT&L) on major acqusitiion decisions? - Answers The Defense Acqusition Board (DAB) Who chairs the DAB - Answers The USD (AT&L) chairs the DAB and the C

Montrer plus Lire moins
Établissement
CDFM Module 4
Cours
CDFM Module 4









Oups ! Impossible de charger votre document. Réessayez ou contactez le support.

École, étude et sujet

Établissement
CDFM Module 4
Cours
CDFM Module 4

Infos sur le Document

Publié le
31 janvier 2025
Nombre de pages
15
Écrit en
2024/2025
Type
Examen
Contient
Questions et réponses

Sujets

Aperçu du contenu

CDFM Module 4 Exam Questions and Answers Latest Update 2025 Already Passed

What are Joint Acquisition Programs? - Answers Joint Acquisition Programs is any acqusition system,
subsystem, component, or technology program with astrategy that includes funding by more than one
DoD component during any phase of a system's life cycle.

Who decides to place programs under joint acquisition management? - Answers The MDA decides
whether to place programs under joint management and designates the lead executive DoD component.

What law requires an analysis of potential opportunities of international cooperation? - Answers 10 USC
2350a(e) requires international cooperation consideration in the initial aquisition strategy for a program.

When international programs may be established in the defense acqusition program - Answers Decision
to include international partners needs to be included during development of the initial capabilities
document but no early than the material and solution analysis phase.

When is Earned Value Management (EVM) implemented - Answers EVM is part of program management
. It ensures that cost , schedule and technical aspects of the contract are truly integrated.

In what type of contracts EVM is required - Answers EVM is required on Cost, and/or Incentive contracts
valued at greater than $20M.

What is EVM? - Answers Earned Value Management is a tool that

1. Relates the scope of the work to its associated budgets and schedule.

2. Measures the work progress in objective terms

3. States that value of the work completed in dollars and other measurable units.

What are EVM techniques? - Answers Correlate the budgeted cost of worked scheduled with the budget
cost of work performed (BCWP)

1. 0/100 Earned Value Technique

2. Percent Start/Percent Finish EV Technique (50/50) (25/75) (80/20)

3. Percent Complete

4. Units Completed

5. Equivalent Units

Describe the Percent Start/Percent Finish EV Technique - Answers Is an objective earned value
technique tied to the start and completion of a work package task, often referred to % assigned to the
start and finish milestone such as (50/50...)

, Thsi technique tends to overstate performance in the first half of the period of performance and
uderstate performance in the last half.

What is the most important step in EVM system? - Answers Is the establishment of the Performance
Measurement Baseline (PMB)or the Budgeted Cost of Work Schedule (BCWS)

What is the PMB in and EVM? - Answers The PMB includes the undistributed budget, all summary level
planning package budgets, and all control account budgets. It does not include management reserve.

What is the final step of the PMB? - Answers Is to classify work, to allocate the budget and to time phase
the control account work package budgets. This last phase is calculate BWCS

How do we classify work packages in EVM? - Answers in 3 categories, Discrete, apportioned effort, and
level of effort.

Describe the realignment of the PMB - Answers Rebaselining, Replanning, and Reprogramming

What is Reprogramming? - Answers Reprogramming is a comprehensive realignment of the remaining
performance measurement baseline that results in a total budget and/or total schedule that exceeds the
contractual requirements. It is the process that results in an Over-Target Baseline or OTB and an Over-
Target Schedule OTS.

Schedule Performance Index (SPI) formula - Answers SPI=BCWP/BCWS

Estimate at Completion (EAC) formula - Answers EAC=ACWP+[(BAC-BCWP)/(Performance Factor)]

EAC Compsite formula - Answers ACWPcum+[(BAC-BCWPcum)/(CPIcum*SPIcum)]

Upper Value (worst case)

EVM Terminology - Answers EAC=Estimate at Completion

BAC=Budget at Completion(current)

BCWS=Budget Cost of Work Scheduled (current)

BWCP=Budget Cost of Work Performed (earned value)

ACWP=Actual Cost of Work Performed

What is the Contractor Cost and Software Data Reporting (CSDR) - Answers The CSDR system involves
two formal contractor reports, the COntractor Cost Data Report (CCDR) and the Software Resources
Data Report (SRDR)

What is Contract Performance Report (CPR) - Answers The PM should obtain from the contractor a CPR
(DD form 2734) on all contracts the meet or exceed EVMS dollar thresholds and require EVMS
compliance. The CPR provides contract cost and schedule performance for program mangement.

Faites connaissance avec le vendeur

Seller avatar
Les scores de réputation sont basés sur le nombre de documents qu'un vendeur a vendus contre paiement ainsi que sur les avis qu'il a reçu pour ces documents. Il y a trois niveaux: Bronze, Argent et Or. Plus la réputation est bonne, plus vous pouvez faire confiance sur la qualité du travail des vendeurs.
TutorJosh Chamberlain College Of Nursing
Voir profil
S'abonner Vous devez être connecté afin de suivre les étudiants ou les cours
Vendu
350
Membre depuis
1 année
Nombre de followers
16
Documents
29222
Dernière vente
4 heures de cela
Tutor Joshua

Here You will find all Documents and Package Deals Offered By Tutor Joshua.

3.6

55 revues

5
19
4
14
3
12
2
0
1
10

Récemment consulté par vous

Pourquoi les étudiants choisissent Stuvia

Créé par d'autres étudiants, vérifié par les avis

Une qualité sur laquelle compter : rédigé par des étudiants qui ont réussi et évalué par d'autres qui ont utilisé ce document.

Le document ne convient pas ? Choisis un autre document

Aucun souci ! Tu peux sélectionner directement un autre document qui correspond mieux à ce que tu cherches.

Paye comme tu veux, apprends aussitôt

Aucun abonnement, aucun engagement. Paye selon tes habitudes par carte de crédit et télécharge ton document PDF instantanément.

Student with book image

“Acheté, téléchargé et réussi. C'est aussi simple que ça.”

Alisha Student

Foire aux questions