1 of 336
Term
What must happen when an issue is likely to result in a change of
scope?
A The issue owner is consulted,
B A decision regarding the issue is deferred.
C The issue is rejected and the owner is informed.
D The issue needs to be progressed through change control.
,Give this one a try later!
D C
B A
Don't know?
2 of 336
Term
How can the project manager ensure a sound stakeholder
environment?
A Ensure that stakeholders who oppose the project are not involved
B Develop an environment where all stakeholder's needs are satisfied.
C Develop ways of understanding the needs of stakeholders.
D Ensure that the influence stakeholders have is reduced.
Give this one a try later!
B A
C D
Don't know?
, 3 of 336
Term
The role of a leader includes:
a. effectively managing risks.
b. selecting the project team.
c. coaching and mentoring project staff.
d. producing accurate project reports.
Give this one a try later!
D B
C A
Don't know?
4 of 336
Term
When is it best to carry out a benefit review?
A At 6—12 months after handover.
B At various stages prior to handover.
C At the concept phase when developing the business case
D At various stages through deployment
, Give this one a try later!
D B
A C
Don't know?
5 of 336
Term
Which of the following is not an output of a critical path analysis?
a. Total and free float.
b. Earliest start time and latest finish time of activities.
c. Project completion time.
d. Cost-benefit analysis.
Give this one a try later!
C B
D A
Don't know?
Term
What must happen when an issue is likely to result in a change of
scope?
A The issue owner is consulted,
B A decision regarding the issue is deferred.
C The issue is rejected and the owner is informed.
D The issue needs to be progressed through change control.
,Give this one a try later!
D C
B A
Don't know?
2 of 336
Term
How can the project manager ensure a sound stakeholder
environment?
A Ensure that stakeholders who oppose the project are not involved
B Develop an environment where all stakeholder's needs are satisfied.
C Develop ways of understanding the needs of stakeholders.
D Ensure that the influence stakeholders have is reduced.
Give this one a try later!
B A
C D
Don't know?
, 3 of 336
Term
The role of a leader includes:
a. effectively managing risks.
b. selecting the project team.
c. coaching and mentoring project staff.
d. producing accurate project reports.
Give this one a try later!
D B
C A
Don't know?
4 of 336
Term
When is it best to carry out a benefit review?
A At 6—12 months after handover.
B At various stages prior to handover.
C At the concept phase when developing the business case
D At various stages through deployment
, Give this one a try later!
D B
A C
Don't know?
5 of 336
Term
Which of the following is not an output of a critical path analysis?
a. Total and free float.
b. Earliest start time and latest finish time of activities.
c. Project completion time.
d. Cost-benefit analysis.
Give this one a try later!
C B
D A
Don't know?