Dynamic Systems Development Method (DSDM) - answer A method
with the principle 'Focus on the business need' and not a PRINCE2
principle. It is a separate agile approach. Ref E.6, tab 7.1
Kanban Method - answer A method with the core practice 'Limit WIP'
and foundation principle 'Start with what you do now'. It is not a
PRINCE2 principle and is used in agile project management. Ref E.7,
tab 7.1
PRINCE2 principle: Focus on products - answer A principle focusing
on product descriptions for prioritization and flexibility in delivery
within the PRINCE2 framework. Ref tab 7.1
Purpose of the risk theme - answer To identify, assess, and control
uncertainty to improve project success within the PRINCE2
framework. Ref tab 5.1
Purpose of the 'managing a stage boundary' process - answer To
provide the project board with information for review, approval of
the next stage plan, and confirmation of continued business
justification and acceptability of risks within the PRINCE2
framework. Ref 21.1
Project product description - answer A special form defining what
the project must deliver for acceptance and verification within the
PRINCE2 framework. Ref A.21.1