100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

ACI Grade 1 Field Testing Certification Practice Test - Irving Questions and Answers 100% Solved correctly

Rating
-
Sold
-
Pages
10
Grade
A+
Uploaded on
18-12-2024
Written in
2024/2025

ACI Grade 1 Field Testing Certification Practice Test - Irving Questions and Answers 100% Solved correctly It is allowable to remove the temperature measuring devices from the freshly mixed concrete to read the temperature if you cannot see the reading. (T or F) - ANSWER -False The maximum allowable time between obtaining the first and last portions of the composite sample may not exceed 5 minutes. (T or F) - ANSWER -False Start molding specimens for strength tests within 30 minutes after fabricating the composite sample. (T or F) - ANSWER -False (15 mins) The composite concrete sample must be protected from sun, wind, contamination and rapid evaporation. (T or F) - ANSWER -False (Contamination and rapid evaporation) If the concrete contains aggregates larger than those that are appropriate for a size of mold or equipment used, the sample should be wet-sieved before making the test. (T or F) - ANSWER -False (wet screened) The composite sample not be remixed before beginning any tests. (T or F) - ANSWER -False Sampling should normally be performed, as the concrete is discharged from the mixer. (T or F) - ANSWER -True ASTM Method C172 includes the sampling from stationary mixers, paving mixers, truck mixers, agitators, and non-agitating equipment. (T or F) - ANSWER -True After sampling is completed, start the tests for slump and air content within: - ANSWER -None of the above (5 mins) In any case, do not obtain samples until: - ANSWER -All the water and admixtures have been added to the concrete No samples shall be taken before ______ or after ______ of the batch has been discharged. - ANSWER - When strength tests are to be made, the minimum size of the composite sample shall be: - ANSWER -1 cubic foot Sample the concrete from the chute of a truck mixer by: - ANSWER - Fresh concrete to be tested at the job site should be sampled from: - ANSWER Two or more regularly spaced intervals during discharge of the middle portion of the batch The elapsed time between obtaining the first and final portions of the composite sample, according to ASTM C172, shall not exceed: - ANSWER -None of the above The sides of the slump cone should be tapped with the mallet to consolidate the concrete in the mold. (T or F) - ANSWER -False For the slump test, when Rodding the second layer and the top layer, the tamping rod should just penetrate into the underlying layer. (T or F) - ANSWER -True According to ASTM C143, it is permissible to use a mold, which clamps to a nonabsorbent base. (T or F) - ANSWER -True When filling the final layer of the slump cone, never heap the concrete above the top of the mold. (T or F) - ANSWER -False The filling of the slump cone should be done in three layers of equal height. (T or F) - ANSWER -False ASTM C1064 states the container used to measure temperature of concrete must be large enough to provide at least 5 inches of concrete around the sensor. (T or F) - ANSWER - Calibrate the temperature measuring device at least __________, or whenever there is a question of accuracy. - ANSWER -Annually After the thermometer is placed in the concrete: - ANSWER -Gently press concrete around the thermometer According to ASTM C1064, what is one reason to take the temperature of concrete? - ANSWER -Verify conformance The slump test may be done on any flat surface. (T or F) - ANSWER -False When filling the slump cone, each layer should be rodded 25 times. (T or F) - ANSWER -True The slump cone is filled in three layers of equal volume. (T or F) - ANSWER True Concrete should be removed from around the base before the cone is lifted. (T or F) - ANSWER -True The slump cone should be raised carefully, vertically upward, in a steady motion in ________ Seconds - ANSWER -3 to 7 The elapsed time between the start of filling the slump cone and the removal of the cone must be no more than: - ANSWER -2 1/2 minutes The slump should be measured to the nearest - ANSWER -Quarter of an inch In order to determine slump, you should measure the vertical distance from: - ANSWER -Top of the mold to the displaced original center of the top surface For concrete with aggregates less than 3 inches, the thermometer must remain in the

Show more Read less
Institution
ACI Grade 1 Field
Course
ACI Grade 1 Field









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
ACI Grade 1 Field
Course
ACI Grade 1 Field

Document information

Uploaded on
December 18, 2024
Number of pages
10
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

ACI Grade 1 Field Testing Certification Practice Test -
Irving Questions and Answers 100% Solved correctly


It is allowable to remove the temperature measuring devices from the freshly
mixed concrete to read the temperature if you cannot see the reading. (T or F) -
ANSWER -False

The maximum allowable time between obtaining the first and last portions of the
composite sample may not exceed 5 minutes. (T or F) - ANSWER -False

Start molding specimens for strength tests within 30 minutes after fabricating the
composite sample. (T or F) - ANSWER -False (15 mins)

The composite concrete sample must be protected from sun, wind, contamination
and rapid evaporation. (T or F) - ANSWER -False (Contamination and rapid
evaporation)

If the concrete contains aggregates larger than those that are appropriate for a size
of mold or equipment used, the sample should be wet-sieved before making the
test. (T or F) - ANSWER -False (wet screened)

The composite sample not be remixed before beginning any tests. (T or F) -
ANSWER -False

Sampling should normally be performed, as the concrete is discharged from the
mixer. (T or F) - ANSWER -True

ASTM Method C172 includes the sampling from stationary mixers, paving
mixers, truck mixers, agitators, and non-agitating equipment. (T or F) - ANSWER
-True

After sampling is completed, start the tests for slump and air content within: -
ANSWER -None of the above (5 mins)

, In any case, do not obtain samples until: - ANSWER -All the water and
admixtures have been added to the concrete

No samples shall be taken before ______ or after ______ of the batch has been
discharged. - ANSWER -

When strength tests are to be made, the minimum size of the composite sample
shall be: - ANSWER -1 cubic foot

Sample the concrete from the chute of a truck mixer by: - ANSWER -

Fresh concrete to be tested at the job site should be sampled from: - ANSWER
Two or more regularly spaced intervals during discharge of the middle portion of
the batch

The elapsed time between obtaining the first and final portions of the composite
sample, according to ASTM C172, shall not exceed: - ANSWER -None of the
above

The sides of the slump cone should be tapped with the mallet to consolidate the
concrete in the mold. (T or F) - ANSWER -False

For the slump test, when Rodding the second layer and the top layer, the tamping
rod should just penetrate into the underlying layer. (T or F) - ANSWER -True

According to ASTM C143, it is permissible to use a mold, which clamps to a
nonabsorbent base. (T or F) - ANSWER -True

When filling the final layer of the slump cone, never heap the concrete above the
top of the mold. (T or F) - ANSWER -False

The filling of the slump cone should be done in three layers of equal height. (T or
F) - ANSWER -False
$6.89
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
ExamMastery

Get to know the seller

Seller avatar
ExamMastery Academy Of Art University
View profile
Follow You need to be logged in order to follow users or courses
Sold
0
Member since
1 year
Number of followers
0
Documents
56
Last sold
-
ExamSolutions

All You Need To Pass Your Exams

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions