Test pressure gauges shall be capable of being read within ___% of test pressure - (answers)90-
110
Pressure gauges used on test equipment shall be calibrated at least - (answers)Semi-annually
The temp used for drying hydro equipment shall not exceed _________ degrees inside the shell -
(answers)150 degrees
The equipment for hydrostatic testing of high pressure cylinders and cartridges (dot 3series) shall
meet the specifications of - (answers)Methods of hydrostatic testing of compressed gas cylinders
A hydrostatic test pump, hand or power operated shall be capable of producing not less than
__________ of the test pressure and shall include appropriate check valves and fittings -
(answers)150 percent
Dry chemical, stored pressure, with mild steel shells, brazed brass shells, or aluminum shells -
(answers)Hydro every 12 years
Dry chemical, stored pressure, cartridge or cylinder operated with mild steel shells need to be
inspected how often?? - (answers)12 yr intervals everything else is 5yr
How often do dry chemicals with stainless steel shells need to be inspected - (answers)Every 5
years
, 2
If, at any time, a fire extinguisher shows evidence of ___________________________ to the
extent as to indicate weakness, it shall be condemned or hydrostati- cally retested -
(answers)dents,
mechanical injury,
or corrosion
The pressure in a hydrostatic test of a cylinder shall be maintained for a minimum of
__________ seconds - (answers)30
All valves, internal parts, and hose assemblies shall be removed, and the fire extinguisher shall
be emptied before testing, clear of any extinguishing agent. true or false? - (answers)True
All tests shall be conducted using test fittings and adapters. true or false? - (answers)True
What shall be cause for rejection or retest? - (answers)drop in pressure of test gauge indicating a
leak
The hydrostatic testing of HIGH PRESSURE cylinders and cartridges shall be in accordance
with the procedures of _________ - (answers)TC, DOT and CGA C-1
For hose test, Pressure shall be applied at a rate of rise such that the test pressure is reached
in____________. - (answers)1 minute
Where pressure is not specified on the extinguisher nameplate the extinguisher shall be tested at
the factory test pressure, not to exceed_________ the extinguisher service pressure. - (answers)3
times
TEXAS FIRE EXTINGUISHER EXAM NEWEST 2025
COMPLETE ACTUAL QUESTIONS AND CORRECT
VERIFIED ANSWERS/ALREADY GRADED A+||BRAND
NEW!!!
Test pressure gauges shall be capable of being read within ___% of test pressure - (answers)90-
110
Pressure gauges used on test equipment shall be calibrated at least - (answers)Semi-annually
The temp used for drying hydro equipment shall not exceed _________ degrees inside the shell -
(answers)150 degrees
The equipment for hydrostatic testing of high pressure cylinders and cartridges (dot 3series) shall
meet the specifications of - (answers)Methods of hydrostatic testing of compressed gas cylinders
A hydrostatic test pump, hand or power operated shall be capable of producing not less than
__________ of the test pressure and shall include appropriate check valves and fittings -
(answers)150 percent
Dry chemical, stored pressure, with mild steel shells, brazed brass shells, or aluminum shells -
(answers)Hydro every 12 years
Dry chemical, stored pressure, cartridge or cylinder operated with mild steel shells need to be
inspected how often?? - (answers)12 yr intervals everything else is 5yr
How often do dry chemicals with stainless steel shells need to be inspected - (answers)Every 5
years
, 2
If, at any time, a fire extinguisher shows evidence of ___________________________ to the
extent as to indicate weakness, it shall be condemned or hydrostati- cally retested -
(answers)dents,
mechanical injury,
or corrosion
The pressure in a hydrostatic test of a cylinder shall be maintained for a minimum of
__________ seconds - (answers)30
All valves, internal parts, and hose assemblies shall be removed, and the fire extinguisher shall
be emptied before testing, clear of any extinguishing agent. true or false? - (answers)True
All tests shall be conducted using test fittings and adapters. true or false? - (answers)True
What shall be cause for rejection or retest? - (answers)drop in pressure of test gauge indicating a
leak
The hydrostatic testing of HIGH PRESSURE cylinders and cartridges shall be in accordance
with the procedures of _________ - (answers)TC, DOT and CGA C-1
For hose test, Pressure shall be applied at a rate of rise such that the test pressure is reached
in____________. - (answers)1 minute
Where pressure is not specified on the extinguisher nameplate the extinguisher shall be tested at
the factory test pressure, not to exceed_________ the extinguisher service pressure. - (answers)3
times