Arcs in a project network indicate a. completion times. b. precedence relationships. c. activities. d. None of the alternatives above is correct.2. Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12, 15, and 10, then the earliest ...