QSP EXAM QUESTIONS 2025 WITH GUARANTEED ACCURATE ANSWERS |VERIFIED
When does the CGP apply? - ACCURATE ANSWERS✔✔ Any
construction or demolition of one acre or more.
Activities under the CGP include:
a. Routine maintenance to maintain original line and grade, hydraulic
capacity, or original purpose of the facility.
b. Disturbances to land surfaces solely related to agricultural operations.
c. Clearing and grading 2 acres of land
d. Discharges of storm water from areas on tribal lands. - ACCURATE
ANSWERS✔✔ C
TRUE OR FALSE: if construction of an LUP will occur across several
properties, the utility company, municipality, or other public/private
, company/agency that owns or operates the LUP project is responsible
for obtaining coverage - ACCURATE ANSWERS✔✔ True
Risk Level 2 monitoring requirements include:
a. Effluent sampling where applicable
b. Sampling for pH and turbidity
c. Sampling for pH, turbidity, and suspended sediments - ACCURATE
ANSWERS✔✔ B
All NAL data must be uploaded within ___ after NAL exceedance has
been identified
a. 24 hours
b. 1 week
c. 10 days
d. 2 weeks - ACCURATE ANSWERS✔✔ C
Who must file Permit Registration Documents (PRDs) prior to the
commencement of construction activity?
a. Qualified SWPPP Developer (QSD)
b. Legally Responsible Person (LRP) or the LRP's Approved Signatory
c. Qualified SWPPP Practitioner (QSP)
d. The CEO - ACCURATE ANSWERS✔✔ B