NICET Level 2 Full Exam Practice Questions and Answers 100% Pass You are inspecting a construction site and notice that the soil appears to be a fine-grained, cohesive material with good bearing capacity. What type of soil is this likely to be? a. Clay b. Sand c. Gravel d. Loam - ANSWER-a. Clay You are inspecting the clearing and grubbing of a construction site and notice that a large tree has been removed within the limits of disturbance. What should you do? a. Notify the project manager and request that a replacement tree be planted b. Document the removal in the construction logs and move on Copyright ©EMILLECT 2024. ALL RIGHTS RESERVED. Page 2/103 c. Issue a stop work order until a replacement tree can be planted d. Request that the tree be replaced, but do not issue a stop work order - ANSWER-d. Request that the tree be replaced, but do not issue a stop work order You are inspecting the placement of an embankment and notice that the compaction is below the required specification. What should you do? a. Accept the work and move on b. Notify the project manager and request that the compaction be corrected c. Issue a stop work order until the compaction can be corrected d. Document the issue in the construction logs and move on - ANSWER-b. Notify the project manager and request that the compaction be corrected You are asked to calculate the excavation and embankment quantities for a construction project. What information do you need to complete this task? a. The dimensions of the excavation and embankment areas b. The weight of the soil and other materials Copyright ©EMILLECT 2024. ALL RIGHTS RESERVED. Page 3/103 c. The density of the soil and other materials d. All of the above - ANSWER-d. All of the above You are inspecting a construction site and notice that temporary erosion and sediment controls are not properly installed. What should you do? a. Accept the work and move on b. Notify the project manager and request that the controls be corrected c. Issue a stop work order until the controls can be corrected d. Document the issue in the construction logs and move on - ANSWER-c. Issue a stop work order until the controls can be corrected You are inspecting the placement of a subgrade and notice that the undercutting is not to the specified depth. What should you do? a. Accept the work and move on b. Notify the project manager and request that the undercutting be corrected c. Issue a stop work order until the undercutting can be c

Meer zien Lees minder
Instelling
Nicet
Vak
Nicet











Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
Nicet
Vak
Nicet

Documentinformatie

Geüpload op
26 november 2024
Aantal pagina's
103
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

NICET Level 2 Full Exam Practice Questions and
Answers 100% Pass


You are inspecting a construction site and notice that the soil appears to be

a fine-grained, cohesive material with good bearing capacity. What type of

soil is this likely to be?


a. Clay


b. Sand


c. Gravel


d. Loam - ANSWER✔✔-a. Clay


You are inspecting the clearing and grubbing of a construction site and

notice that a large tree has been removed within the limits of disturbance.

What should you do?


a. Notify the project manager and request that a replacement tree be

planted


b. Document the removal in the construction logs and move on


Copyright ©EMILLECT 2024. ALL RIGHTS RESERVED. Page 1/103

,c. Issue a stop work order until a replacement tree can be planted


d. Request that the tree be replaced, but do not issue a stop work order -

ANSWER✔✔-d. Request that the tree be replaced, but do not issue a stop

work order


You are inspecting the placement of an embankment and notice that the

compaction is below the required specification. What should you do?


a. Accept the work and move on


b. Notify the project manager and request that the compaction be corrected


c. Issue a stop work order until the compaction can be corrected


d. Document the issue in the construction logs and move on -

ANSWER✔✔-b. Notify the project manager and request that the

compaction be corrected


You are asked to calculate the excavation and embankment quantities for a

construction project. What information do you need to complete this task?


a. The dimensions of the excavation and embankment areas


b. The weight of the soil and other materials


Copyright ©EMILLECT 2024. ALL RIGHTS RESERVED. Page 2/103

,c. The density of the soil and other materials


d. All of the above - ANSWER✔✔-d. All of the above


You are inspecting a construction site and notice that temporary erosion

and sediment controls are not properly installed. What should you do?


a. Accept the work and move on


b. Notify the project manager and request that the controls be corrected


c. Issue a stop work order until the controls can be corrected


d. Document the issue in the construction logs and move on -

ANSWER✔✔-c. Issue a stop work order until the controls can be corrected


You are inspecting the placement of a subgrade and notice that the

undercutting is not to the specified depth. What should you do?


a. Accept the work and move on


b. Notify the project manager and request that the undercutting be

corrected


c. Issue a stop work order until the undercutting can be corrected




Copyright ©EMILLECT 2024. ALL RIGHTS RESERVED. Page 3/103

, d. Document the issue in the construction logs and move on -

ANSWER✔✔-b. Notify the project manager and request that the

undercutting be corrected


You are asked to determine the acceptability of the results of a soil

compaction test. What criteria should you use to make this determination?


a. The compaction meets or exceeds the specified density


b. The compaction meets or exceeds the specified moisture content


c. The compaction meets or exceeds both the specified density and

moisture content


d. The compaction meets or exceeds the specified density or moisture

content - ANSWER✔✔-c. The compaction meets or exceeds both the

specified density and moisture content


You are inspecting the placement of an aggregate subbase and notice that

the finish tolerances are not being met. What should you do?


a. Accept the work and move on


b. Notify the project manager and request that the finish tolerances be

corrected
Copyright ©EMILLECT 2024. ALL RIGHTS RESERVED. Page 4/103

Beoordelingen van geverifieerde kopers

Alle 2 reviews worden weergegeven
4 maanden geleden

10 maanden geleden

4.0

2 beoordelingen

5
1
4
0
3
1
2
0
1
0
Betrouwbare reviews op Stuvia

Alle beoordelingen zijn geschreven door echte Stuvia-gebruikers na geverifieerde aankopen.

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Emillect West Virginia University
Bekijk profiel
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
28
Lid sinds
1 jaar
Aantal volgers
2
Documenten
3004
Laatst verkocht
1 maand geleden
GOLDEN ORCHIDS STORE.

On this page, you find all documents, package deals, and flashcards offered by seller Emillect.

3.0

4 beoordelingen

5
1
4
0
3
2
2
0
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen