Fundamentals: Level of Architecture Review
True or False: At the Company level, users will only have access to view projects to which
they have been specifically granted access to by a company/project administrator. -
CORRECT ANSWER✔✔- True
Fundamentals: Level of Architecture Review
What information can be found in the Commitment Summary Report? - CORRECT
ANSWER✔✔- a. A financial overview of commitments, commitment change orders, and
payments
Fundamentals: Level of Architecture Review
What information is NOT displayed on a project's Home tab? - CORRECT ANSWER✔✔- e.
All of the above appear on the Project's Home tab
(Items that were recently changed in the project, the daily weather based on the project's zip
code, the featured image of a project, a list of your open items)
Fundamentals: Documents Review
How do you make an uploaded file or folder private? - CORRECT ANSWER✔✔- d. All of
the above
(Click the padlock icon so that it's locked/closed, move it into a private folder, mark the
"Make Private" checkbox under a document's "File Permissions" section)
Fundamentals: Documents Review
What is the best way to be notified of changes made to a file or folder? - CORRECT
ANSWER✔✔- c. Use the built-in file tracking feature
Fundamentals: Documents Review
True or False: Previously uploaded versions/revisions of a file are preserved in Procore and
are available for download in the file's Version Log. - CORRECT ANSWER✔✔- True
, Fundamentals: Documents Review
How do you add a document to a project? - CORRECT ANSWER✔✔- e. All of the above
(Send a file to the project's unique email address, upload a file using Procore's Windows
Desktop application, Procore Drive, drag and drop a file into a folder's designated "Upload
Queue" section, or click the "Browse" button to select a file from your local computer)
Fundamentals: Documents Review
True or False: There is no way to validate whether or not a user (who has access to view the
file) has downloaded the file from Procore. - CORRECT ANSWER✔✔- False
Fundamentals: Upload Drawings Review
True or False: If you upload a multi-page drawing set (as a single PDF), Procore will
automatically split up the set into individual drawings. - CORRECT ANSWER✔✔- a. True
Fundamentals: Upload Drawings Review
Once a drawing has been reviewed and published, which of the following data fields can still
be edited/changed?
Number
Title
Revision Number
Dates
Discipline - CORRECT ANSWER✔✔- c. All of the drawing fields listed above
Fundamentals: Upload Drawings Review
True or False: When you review uploaded drawings and manually correct/edit the auto-filled
drawing title and/or number, Procore can dynamically readjust its processing algorithm for
the remaining drawings based on your changes. - CORRECT ANSWER✔✔- a. True
Fundamentals: Upload Drawings Review
When reviewing an uploaded drawing, you can perform the following actions, EXCEPT: -
CORRECT ANSWER✔✔- c. Add markups to the drawing