When using FAR part 12 procedures, the technical evaluation would normally include
examination of such things as product literature, product samples (if requested), technical
features, and:
Management plans
Manufacturing plans
Quality assurance plans
Warranty provisions - ✔✔Warranty provisions
Provisions and clauses should be incorporated by reference in solicitations and contracts:
Unless they are used with more than one alternate, then full text is required
To the maximum practical extent, rather than being incorporated in full text
Unless they contain a blank within the text that the contracting officer must fill in prior to
award
Unless the uniform contract format (UCF) applies - ✔✔To the maximum practical extent,
rather than being incorporated in full text
Which offerors receive an amendment on a solicitation that has yet to close?
, All parties in the competitive range
None. Solicitations are modified, not amended
All parties receiving the solicitation
None. Solicitations can't be amended until they have closed - ✔✔All parties receiving the
solicitation
The purpose of exchanging information with industry before receipt of proposals is to:
Always obtain the lowest price for Government requirements
Find a sole source contractor to meet the Government's requirements
Negotiate the best deal in response to the Government's requirements
Improve the understanding of Government requirements and industry capabilities -
✔✔Improve the understanding of Government requirements and industry capabilities
Which of the following is the correct title of a solicitation for negotiated procedures?
Invitation for Proposals
Request for Proposals
Request for Cost Proposals
ANSWERS 2024-2025
When using FAR part 12 procedures, the technical evaluation would normally include
examination of such things as product literature, product samples (if requested), technical
features, and:
Management plans
Manufacturing plans
Quality assurance plans
Warranty provisions - ✔✔Warranty provisions
Provisions and clauses should be incorporated by reference in solicitations and contracts:
Unless they are used with more than one alternate, then full text is required
To the maximum practical extent, rather than being incorporated in full text
Unless they contain a blank within the text that the contracting officer must fill in prior to
award
Unless the uniform contract format (UCF) applies - ✔✔To the maximum practical extent,
rather than being incorporated in full text
Which offerors receive an amendment on a solicitation that has yet to close?
, All parties in the competitive range
None. Solicitations are modified, not amended
All parties receiving the solicitation
None. Solicitations can't be amended until they have closed - ✔✔All parties receiving the
solicitation
The purpose of exchanging information with industry before receipt of proposals is to:
Always obtain the lowest price for Government requirements
Find a sole source contractor to meet the Government's requirements
Negotiate the best deal in response to the Government's requirements
Improve the understanding of Government requirements and industry capabilities -
✔✔Improve the understanding of Government requirements and industry capabilities
Which of the following is the correct title of a solicitation for negotiated procedures?
Invitation for Proposals
Request for Proposals
Request for Cost Proposals