Contingency Analysis & Reliability

What is an Operating Instruction?

- Any conversation between two or more parties related to the reliability of the BES
- A documented procedure or process for addressing an IROL exceedance
- Real-time Operating personnel command to change or preserve the state of an
element of the BES
- Managers command to shed load - answer- Real-time Operating personnel command
to change or preserve the state of an element of the BES

A Generator Operator receives an Operating Instruction from its Transmission Operator
to bring on additional generation to mitigate a low voltage situation. The Generator
Operator must comply with the Operating Instruction unless:

- The Generator Operator disagrees with the Operating Instruction
- It results in safety concerns or environmental violations
- It has serious financial implications
- The operator is in the middle of shift turnover - answer- It results in safety concerns or
environmental violations

TOP 001, R3

The Transmission Operator experiences an unexpected line outage which results in the
subsequent loading of a parallel line at 101% of its SOL, what action should the
Transmission Operator take?

- Inform the Reliability Coordinator
- Wait until load decreases
- Take the appropriate action to return the system to within normal limits
- Open the overloaded line - answer- Inform the Reliability Coordinator
- Take the appropriate action to return the system to within normal limits

Following a contingency or other event resulting in an Interconnection Reliability
Operating Limit (IROL) violation, the Transmission Operator shall return to within the
IROL as soon as possible, but no longer than ______.

- 15 minutesIts
- IROL Tv
- 30 minutes
- 60 minutes - answerIts IROL Tv

,A Transmission Operator performs a Real-time Assessment that identifies a SOL
exceedance. What should the Transmission Operator do next?

- Shed load required to return to the SOL limit
- Contact the Reliability Coordinator and ask for assistance
- Isolate the line with the exceedance
- Initiate its Operating Plan to mitigate the SOL exceedance - answer- Initiate its
Operating Plan to mitigate the SOL exceedance

When another Transmission Operator requests emergency actions to be implemented
in your area, what is the expectation?

- The requesting TOP has also implemented emergency actions
- You assist immediately without asking questions
- The Reliability Coordinator must make the request
- Uncontrolled cascading outages are imminent - answer- The requesting TOP has also
implemented emergency actions

Which of the following actions would a Transmission Operator be expected to take, or
direct others to take, to mitigate SOL and IROL violations? Select all that apply.

- Shed load
- Change limit
- Disconnect from neighbors
- Reduce Interchange
- Change the output of generators - answer- Shed load
- Reduce Interchange
- Change the output of generators

Why is it necessary to report SOL and IROL exceedances to the Reliability
Coordinator?

- The Reliability Coordinator will then evaluate actions being taken and direct additional
corrective actions as needed
- To shift responsibility for fixing the issue to the Reliability Coordinator
- The Reliability Coordinator will then notify neighboring Reliability Coordinators to open
various circuit breakers
- The Reliability Coordinator will then determine consequences and penalties for the
exceedance - answer- The Reliability Coordinator will then evaluate actions being taken
and direct additional corrective actions as needed

Which are the three types of limits to consider when determining system limits?

- Voltage
- Angle stability
- Thermal

, - Impedance - answer- Voltage
- Angle stability
- Thermal

A contingency results in the exceedance of an IROL. What could be the result if the
IROL is allowed to be exceeded longer than its Tv?

- Failure of the transmission line
- Loss of power to a local area
- Interruption of power to a large part of the BES
- Voltage below its normal Operating range - answer- Interruption of power to a large
part of the BES

A Transmission Operator has scheduled a short, temporary outage of the SCADA
system for a software update at 22:00 tonight. Which of the following actions is required
of the Transmission Operator?

- Request permission from NERC Operating Committee
- Notify the Reliability Coordinator and known impacted entities of the outage
- Fully implement the Backup Control Center
- Request a level 1 Energy Emergency Alert - answer- Notify the Reliability Coordinator
and known impacted entities of the outage

A transmission line trip results in a SOL exceedance and the Transmission Operator
implements the Operating Plan for the SOL. What should the Transmission Operator do
next?

- Update the map board
- Inform the Reliability Coordinator of actions taken
- Make a fresh pot of coffee
- File event report to NERC within 24 hours - answer- Inform the Reliability Coordinator
of actions taken

No IROL can have an IROL TV that exceeds __________?

15 minutes
30 minutes
90 minutes
60 minutes - answer30 minutes

A Transmission Operator notified the Generator Operator to change the MW output of
their hydro plant to relieve an overloaded transmission line. That is an example of which
of the following?

Operating Plan
Operating Instruction

Escuela, estudio y materia

Institución
SOS NERC
Grado
SOS NERC

Información del documento

Subido en
7 de noviembre de 2024
Número de páginas
20
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
julianah420 Phoenix University
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
679
Miembro desde
3 año
Número de seguidores
328
Documentos
34817
Última venta
6 días hace
NURSING,TESTBANKS,ASSIGNMENT,AQA AND ALL REVISION MATERIALS

On this page, you find all documents, package deals, and flashcards offered by seller julianah420

4.2

154 reseñas

5
102
4
21
3
10
2
5
1
16

Documentos populares

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes