Before leveling a mobile crane on outriggers, an operator should ensure: - ANSWER-there is no weight of the crane bearing on any tires Operating a mobile crane with a long boom, on uneven ground, what support condition should be considered? - ANSWER-Keeping 90 degree angle between cylinder rod and pad What is the primary purpose fir a rooster sheave or auxiliary boom point sheave? - ANSWER-Separate the boom hoist lines How many randomly broken wires in a lay length must there be on a mobile cranes hoist line, before it should be removed from service? - ANSWER-6 On a mobile crane, how many broken wires are permitted at the end connection of a pendent before it must be taken out of service? - ANSWER-1 Type 1 rotation resistant hoist wire rope has a design factor of: - ANSWER-5 to 1 How many randomly distributed broken wires in rotation- resistant hoist wire rope are considered for replacement? - ANSWER-2 broken wires in 6 rope diameters The term net capacity is best defined by which of the terms listed below? - ANSWER-Gross capacity minus capacity deductions

Show more Read less
Institution
NCCCO CORE
Course
NCCCO CORE









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
NCCCO CORE
Course
NCCCO CORE

Document information

Uploaded on
October 25, 2024
Number of pages
13
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

NCCCO CORE Exam Questions With
100% Accurate Answers Rated A+

Before leveling a mobile crane on outriggers, an operator should ensure: - ANSWER-
there is no weight of the crane bearing on any tires



Operating a mobile crane with a long boom, on uneven ground, what support condition
should be considered? - ANSWER-Keeping 90 degree angle between cylinder rod and
pad



What is the primary purpose fir a rooster sheave or auxiliary boom point sheave? -
ANSWER-Separate the boom hoist lines



How many randomly broken wires in a lay length must there be on a mobile cranes
hoist line, before it should be removed from service? - ANSWER-6



On a mobile crane, how many broken wires are permitted at the end connection of a
pendent before it must be taken out of service? - ANSWER-1



Type 1 rotation resistant hoist wire rope has a design factor of: - ANSWER-5 to 1



How many randomly distributed broken wires in rotation- resistant hoist wire rope are
considered for replacement? - ANSWER-2 broken wires in 6 rope diameters



The term net capacity is best defined by which of the terms listed below? - ANSWER-
Gross capacity minus capacity deductions

, Mobile cranes that are set up on barges, shall have a list chart provided by which of the
entities listed below? - ANSWER-Manufacturer



When lifting loads on tires, mobile cranes are rated at what percentage of tipping? -
ANSWER-75%



How does the effective weight of a slowed extension relate to the actual weight of the
extension? - ANSWER-Higher than the actual weight.



When load radius is between radii values, the operator must use the: - ANSWER-longer
radius



Why should only approved attachments or extra counterweights provided by the
manufacturer be placed on the rear of the crane? - ANSWER-They could cause a
backward stability problem.



A mobile crane's jib is offset 15º versus its original 0º offset, but the boom angle
remains unchanged. In this situation, the load radius: - ANSWER-increases



Abruptly stopping a rapid swing on a long-boom mobile crane will produce what major
effect? - ANSWER-Collapsing the boom.



When determining the position to a mobile crane should be left in over night, when high
winds in the forecast the operator should: - ANSWER-Follow the manufacturers
recommendations.



If a mobile crane is NOT set-up level and the operator swings the load from the high
side to the low side, what effect will that have on the radius? - ANSWER-The radius
increase.
$11.49
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
Vaster
5.0
(2)

Also available in package deal

Thumbnail
Package deal
NCCCO EXAM BUNDLE QUESTIONS WITH 100% COMPLETE SOLUTIONS
-
25 2024
$ 271.45 More info

Get to know the seller

Seller avatar
Vaster Stanford University
View profile
Follow You need to be logged in order to follow users or courses
Sold
4
Member since
1 year
Number of followers
1
Documents
794
Last sold
1 month ago

5.0

2 reviews

5
2
4
0
3
0
2
0
1
0

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions