NCCCO Lattice Boom General Knowledge Exam Questions with Verified Answers The lattice boom is designed to take winds of up to 20 mph. from the side plus a full rated load, plus a direct side load equal to what percent of the rated load? - correct answer -2% The part of the load chart governed by stability is based on what percentage of capacity while a crawler crane is working over the side quadrant? - correct answer -A. 75% The most unstable working quadrant for a crawler crane is the; - correct answer -Side

Meer zien Lees minder
Instelling
NCCCO Lattice Boom General Knowledge
Vak
NCCCO Lattice Boom General Knowledge









Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
NCCCO Lattice Boom General Knowledge
Vak
NCCCO Lattice Boom General Knowledge

Documentinformatie

Geüpload op
25 september 2024
Aantal pagina's
5
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

NCCCO Lattice Boom General Knowledge Exam
Questions with Verified Answers

The lattice boom is designed to take winds of up to 20 mph. from the side
plus a full rated load, plus a direct side load equal to what percent of the
rated load? - correct answer -2%
The part of the load chart governed by stability is based on what percentage
of capacity while a crawler crane is working over the side quadrant? -
correct answer -A. 75%
The most unstable working quadrant for a crawler crane is the; - correct
answer -Side
What type of capacity is listed on a crane load chart? - correct answer -Static
If the manufacture of a particular crane does not specifically permit pick
and carry operations what procedure must be followed during this
operation? - correct answer -Don't make any pick and carry lifts
What is the main purpose of a jib/extension? - correct answer -To extend
reach higher or up and over
When the number of layers of rope on a drum increase the line
pull___________. - correct answer -Decreases
When handling boom sections, the best place for slings to be attached is; -
correct answer -At the pin connections at the ends of the top chords
Placing timber blocking under the tips of the tracks on a crawler crane will;
- correct answer -Make the crane more stable
What is the major effect of stopping suddenly a rapid swing while operating
long boom crane? - correct answer -Action may cause the crane boom
collapse and/or overturn the crane
According to B30.10 hooks shall be removed from service when the throat
opening exceeds _____ the original throat opening. - correct answer -5%

, On a crawler crane ground bearing pressure is greatest where? - correct
answer -Over the corner
During disassembly of a long boom, the pendant lines are connected at the
maximum cantilever point and the boom is slightly lifted off the ground,
which boom connection pins are to be removed next? - correct answer -The
bottom pins ahead of the cantilever point
The definition of cantilever of a lattice boom crane is; - correct answer -The
boom suspended past the pendant connections
Most crane manufactures require the load chart capacities must be reduced
when wind speed reaches; - correct answer -20 mph
What chart do you use when operating a crane on a barge; - correct answer -
List chart
According to OSHA, Jibs must have a positive ________ from backwards
overturning - correct answer -Stop
Mobile cranes on barges shall be - correct answer -Physically attached to the
barge
When a crane is properly barricaded, what is the clearance required all the
way around 360 degrees between the superstructure and the barricade
when swung 360 degrees? - correct answer -2 feet
According to ASME B30.5 a fire extinguisher shall have a rating of
__________ and shall be available at all operator's stations or cabs of the
equipment. - correct answer -10 BC or higher
When assembling a lattice boom crane the top pins of the boom sections
should be inserted; - correct answer -First
Block hoisting sheaves should have a minimum pitch diameter of at
least________ the rope diameter. - correct answer -16 times
What is the correct method of checking the brakes of crane that has been
already assembled? - correct answer -Lift the load a few inches off the
ground and apply the brakes

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
SmartScoreAcademics Rasmussen College
Bekijk profiel
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
26
Lid sinds
2 jaar
Aantal volgers
8
Documenten
147
Laatst verkocht
3 maanden geleden

5.0

1 beoordelingen

5
1
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via Bancontact, iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo eenvoudig kan het zijn.”

Alisha Student

Veelgestelde vragen