CCO practice test questions with 100% correct answers 2024/2025 Before crane erection can begin what must be available? - ANSWERSsurface that is firm, drained and graded OSHA 29 CFR 1926.1407 Power Line Safety, Option 1 requires what? - ANSWERSPower lines are de-energize and grounded Before work can begin for a newly erected tower crane what must be done before the crane can begin working? - ANSWERSset load motion limits and safety devices What type of attachment system is used to hold a personnel platform to the crane hook? - ANSWERSMaster link attachment or safety type shackle When should a personnel platform be used? - ANSWERSThere is no other safe way to perform the task OSHA, Cranes and Derricks working in Construction is under what regulation? - ANSWERSOSHA 29 CFR 1926.550 What is the Safety Factor for suspended platform and shackles? - ANSWERS5 to 1 What ASME Standard applies to personnel platforms? - ANSWERSB 30.23 Annual inspection records must be kept for how long? - ANSWERS12 months What ASME Standard applies to Tower Cranes? - ANSWERSB 30.3 Expendable tower base, the tolerance for "plumb" is? - ANSWERS¼ - 10ft.

Show more Read less
Institution
CCO Practice
Course
CCO practice









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
CCO practice
Course
CCO practice

Document information

Uploaded on
September 20, 2024
Number of pages
5
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

CCO practice test questions with 100%
correct answers 2024/2025

Before crane erection can begin what must be available? - ANSWERSsurface that is firm, drained and
graded



OSHA 29 CFR 1926.1407 Power Line Safety, Option 1 requires what? - ANSWERSPower lines are de-
energize and grounded



Before work can begin for a newly erected tower crane what must be done before the crane can begin
working? - ANSWERSset load motion limits and safety devices



What type of attachment system is used to hold a personnel platform to the crane hook? -
ANSWERSMaster link attachment or safety type shackle



When should a personnel platform be used? - ANSWERSThere is no other safe way to perform the task



OSHA, Cranes and Derricks working in Construction is under what regulation? - ANSWERSOSHA 29 CFR
1926.550



What is the Safety Factor for suspended platform and shackles? - ANSWERS5 to 1



What ASME Standard applies to personnel platforms? - ANSWERSB 30.23



Annual inspection records must be kept for how long? - ANSWERS12 months



What ASME Standard applies to Tower Cranes? - ANSWERSB 30.3



Expendable tower base, the tolerance for "plumb" is? - ANSWERS¼ - 10ft.

, Free standing Hammerhead tower crane mast will be "plumbed" to a tolerance of - ANSWERS1 inch=
40ft.



Before crane components are erected they shall be: - ANSWERSVisually inspected for damage from
shipping and handling



Where would the insulating link device be attached? - ANSWERSAttached or installed at the end of load
line and the load



Annual/comprehensive inspection must include the qualified person to perform what? -
ANSWERSFunctional motion testing of the equipment



Rail buffers or rail stops must be placed how far from the end of the travel tracks? - ANSWERS3 ft



Internal climbing crane must be plumbed by using what to hold crane in position? - ANSWERSWedges



What is the maximum rate of wind speed allowed to climb a tower crane? - ANSWERS20 mph



during erection or dismantling operations, who must always be present? - ANSWERSAD director



How many wraps shall remain on the hoist drum according to the Tower Crane Reference Manual? -
ANSWERS3 wraps on the hoist drum



Personnel Platform must be Proof Tested each day before use, how much weight is used and how long
must the test last for? - ANSWERS125% and hold for 5 minutes



OSHA 1926.1407 power line requirements for 1000kv are? - ANSWERSRemain 20' or more from lines



Standing rope or pendant lines must have the following minimum design factor of? - ANSWERS3:1

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Bensuda Oxford University
View profile
Follow You need to be logged in order to follow users or courses
Sold
835
Member since
3 year
Number of followers
445
Documents
20904
Last sold
3 days ago
ECONOMICS,NURSING,BIOLOGY AND ALL REVISION MATERIALS

DEDICATED TO PROVIDE YOU WITH THE BEST LEARNING MATERIALS THAT WILL IMPROVE YOUR GRADES ,WELCOME TO ALIZGRADES AND LETS DO IT TOGETHER!!! GOODLUCK!!!!!!!

3.7

156 reviews

5
72
4
24
3
25
2
11
1
24

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions