In what sort of contract does a contractor take on the least cost risk?
Cost Plus Fixed Fee Contracts:
Unbalanced pricing happens when the entire price appears appropriate, but data
indicates that one or more contract line items are significantly over or
underpriced.
Cost/Price Analysis
-
Communications may be performed to improve the government's knowledge of
proposals, allow for acceptable interpretations of the proposals, or facilitate the
government's evaluation process.
True
1 multiple-choice option.
Before negotiating any pricing action, the contracting officer must first define
pre-negotiation objectives.
True
1 multiple-choice option.
The UCF includes information about a company's size status.
Section K
-
, Who is accountable for making the best-value decision?
Source Select Authority (SSA).
-
Who is the principal business advisor for source selection?
Procurement Contracting Officer (PCO)
-
Which two evaluation factors should be included in each source selection?
Price or Cost and Quality
-
A protest is a ____________ ____________ by a _____________________.
Written objection, interested party.
-
An interested party is a current or future offeror.
True
1 multiple-choice option.
How many protest sites are there?
3
-
To whom should protests to the agency be addressed?
Cost Plus Fixed Fee Contracts:
Unbalanced pricing happens when the entire price appears appropriate, but data
indicates that one or more contract line items are significantly over or
underpriced.
Cost/Price Analysis
-
Communications may be performed to improve the government's knowledge of
proposals, allow for acceptable interpretations of the proposals, or facilitate the
government's evaluation process.
True
1 multiple-choice option.
Before negotiating any pricing action, the contracting officer must first define
pre-negotiation objectives.
True
1 multiple-choice option.
The UCF includes information about a company's size status.
Section K
-
, Who is accountable for making the best-value decision?
Source Select Authority (SSA).
-
Who is the principal business advisor for source selection?
Procurement Contracting Officer (PCO)
-
Which two evaluation factors should be included in each source selection?
Price or Cost and Quality
-
A protest is a ____________ ____________ by a _____________________.
Written objection, interested party.
-
An interested party is a current or future offeror.
True
1 multiple-choice option.
How many protest sites are there?
3
-
To whom should protests to the agency be addressed?