,T01.E06
You have a requirement for repair parts to support routine maintenance services at the
shop on your base. the parts were developed using Government funds and are not
offered to the general public. The estimated dollar value of the acquisition is $275,000.
Which one of the following statements is true? - ANSWER-the use of simplified
acquisition procedures is prohibited.
101.E05
Which one of the following market research results would NOT support a commercial
item determination? - ANSWER-The part was developed using Government funding
and is only sold to DoD agencies.
T02.E02
You have a one time requirement for a purchases of non-commercial supplies with an
estimated value of $235,000. The supplies are not immediately available. Which one of
the following simplified acquisition methods would be the most appropriate to use? -
ANSWER-Purchase order
T03.E03a
You are the contracting office for a firm-fixed-price purchase order for commercial
services with a value of $1,425,000. Your customer has notified you that one of the
contractually required reports accepted by the government was submitted five days late.
You Investigate and verify that the report was submitted late. Which one of the following
statements regarding the nonconforming performance is FALSE? - ANSWER-The
Government must pay for reperformance of the nonconforming service because the
report was accepted.
T01.E06
You have a requirement for water restoration services at your base in Louisiana. Three
services are of a type sold competitively in substantial quantities in the commercial
marketplace base on market prices. The estimated dollar value of the acquisition is
$1,250,000.
Which of the following is true? - ANSWER-the use of simplified acquisition procedures
is authorized.
T03.E03a
, You are the contracting office for a firm-fixed-price purchase order for commercial
supplies with a value of $565,000. Two weeks after delivery and acceptance of the
items, the user complains that the goods are not functioning as expected. You
Investigate and determine that the items are not fully compliant with the specification in
the contract. who would bear the cost of correcting the nonconforming supplies that
were accepted by the Government? - ANSWER-The Contractor
T02.E05b
You just made a purchase for supplies in the amount of $22,300. You solicited
quotations orally from four local sources. Which of the following statements is correct
regarding providing notice to the unsuccessful suppliers? - ANSWER-Notice to the
unsuccessful suppliers will only be given if requested.
T02.E04
You are the contracting officer for a requirement for commercial services with and
estimated value of $780,000. Four quotations were received in response to the
solicitation and market pricing is available. Which one of the following statements about
the price reasonableness determination is most appropriate? - ANSWER-Market
research must be conducted or obtained to support the fair and reasonable
determination.
T03.E02
You are the contracting officer for a firm-fixed-priced services contract valued at
$105,975. Which one of the following statements about closeout is correct? - ANSWER-
The contract is considered closed once you've received evidence of receipt of service
and final payment.
T02.E03a
Which one of the following is NOT one of the first steps taken when questions are
received in response to a solicitation using SAP. - ANSWER-Reviewing the quotations
for responsibility
(1 of 3 known answers)
T01.E04
You have a requirement for administrative support with an estimated value of
$1,500,000. Market research shows numerous potential offerors that are competitive in
terms of market price quality, and delivery. That list of potential offerors includes 4 small
businesses and 8 large businesses. - ANSWER-The entire acquisition must be set