100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

ICC Prestressed Concrete - Codes and Plans Certification Preparation Questions and Answers 100% Solved

Rating
-
Sold
-
Pages
13
Grade
A+
Uploaded on
07-09-2024
Written in
2024/2025

ICC Prestressed Concrete - Codes and Plans Certification Preparation Questions and Answers 100% Solved Module 1. Prestressed concrete is: - The tensioning of steel-stranded cables prior to concrete placement - The tensioning of steel-stranded cables after concrete has been placed and hardened - Concrete that has received a tensile load prior to any service loads Module 1. The use of a prestressed concrete system will achieve the following: - Reduced thickness of concrete, less conventional reinforcing steel and adequate crack control Module 1. Once tensioned, the tensioning cables are held securely in a tensioned state by: Wedges that have been seated Module 1. The end of a cable that terminates within a concrete slab, thus rendering it in accessible from outside the concrete is known as: The dead end Module 1. The presence of sheathing on a wire-stranded cable indicates that: It will be used in an unbonded system application Module 1. The most common post-tension cable tendons in use today are made up of: 7 steel strands of wire wrapped together Module 1. In an unbonded system, the force applied to the concrete after tensioning: Comes from the anchorage zone only Module 2. Post-tension manufacturing plants must be certified by: PTI Unbonded Plant Certification Program Module 2. Prior to cutting the tendon tails after tensioning, the field records of stressing activities must be forwarded to and approved by: The engineer of record Module 2. In the event that a new set of stressing equipment is delivered to the project, this equipment should contain __________ for review prior being used on-site: A current calibration chart relating gauge pressure to force applied Module 2. According to the Field Procedures Manual for Unbonded Single Strand Tendons, all of the following items are necessary for post-tension document control except: A) Concrete Strength Results B) Shipping Lists C) Material Certifications D) Approved Installation Drawings A) Concrete Strength Results Module 2. When reporting stressing results, the following information is necessary to record: A) Jack and gauge serial number B) Elongation measurements and percentage deviation C) Both A and B D) Gauge Manufacturer E) All three, A, B, and D C) Both A and B Module 2. When moving post-tension cables across the site, the use of _______ is permitted. A) Nylon slings, with unloading as close as placement as possible B) Smooth finished chains with limited use C) Epoxy coated high strength wire with limited use D) A large front loader exercising caution Nylon slings, with unloading as close to the placement as possible Module 2. When storing post-tension cables, care must be taken to: Prevent the cables from being exposed to weather elements and moisture Module 2. During deliver, it is the ______________ responsibility to ensure the delivered items match the shipping list. Buyer's Module 2. According to the Field Procedures Manual for Unbonded Single Strand Tendons, the follow documents must be kept on site: 1) Approved Installation Drawings 2) Shipping Lists 3) Material Certifications 4) Jack Calibrations 5) Stressing Records Module 2. Install drawings show: Plan views, elevation views, and details so the subcontractor and inspector can clearly see the tendon layout. This includes tendon profiles, also known as drape. Module 2. Drape Tendon profiles Module 2. Material Certifications Documents that describe the cables' physical properties and factory testing results. Module 2. Stressing records, written by the inspector, should include: - Location of tendons stressed (grid line to grid line) - Type of tendons stressed (banded, uniform, beans, temperature) - Gauge/jack used - Date, time, and weather during stressing - Stressing crew - Elongations based on a traceable numbering system - Any deviations from tolerances Module 2. As an inspector, you should immediately check for ____________ when you see the stressing equipment. I.e., not on the day of stressing. Jack Calibration Records Module 3. On a two-way flat plate, a minimum of ___________ over each column first. A) 2 uniform tendons should be placed B) 1 group of banded tendons should be placed C) 50% of the bottom bars should be placed D) (3) #5 support bars should be placed A) 2 uniform tendons should be placed

Show more Read less
Institution
ICC
Course
ICC









Whoops! We can’t load your doc right now. Try again or contact support.

Document information

Uploaded on
September 7, 2024
Number of pages
13
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

ICC Prestressed Concrete - Codes and
Plans Certification Preparation
Questions and Answers 100% Solved

Module 1. Prestressed concrete is: - answer- The tensioning of steel-stranded cables
prior to concrete placement
- The tensioning of steel-stranded cables after concrete has been placed and hardened
- Concrete that has received a tensile load prior to any service loads

Module 1. The use of a prestressed concrete system will achieve the following: -
answer- Reduced thickness of concrete, less conventional reinforcing steel and
adequate crack control

Module 1. Once tensioned, the tensioning cables are held securely in a tensioned state
by: - answer Wedges that have been seated

Module 1. The end of a cable that terminates within a concrete slab, thus rendering it in
accessible from outside the concrete is known as: - answer The dead end

Module 1. The presence of sheathing on a wire-stranded cable indicates that: - answer
It will be used in an unbonded system application

Module 1. The most common post-tension cable tendons in use today are made up of: -
answer7 steel strands of wire wrapped together

Module 1. In an unbonded system, the force applied to the concrete after tensioning: -
answer Comes from the anchorage zone only

Module 2. Post-tension manufacturing plants must be certified by: - answer PTI
Unbonded Plant Certification Program

Module 2. Prior to cutting the tendon tails after tensioning, the field records of stressing
activities must be forwarded to and approved by: - answer The engineer of record

Module 2. In the event that a new set of stressing equipment is delivered to the project,
this equipment should contain __________ for review prior being used on-site: - answer
A current calibration chart relating gauge pressure to force applied

, Module 2. According to the Field Procedures Manual for Unbonded Single Strand
Tendons, all of the following items are necessary for post-tension document control
except:
A) Concrete Strength Results
B) Shipping Lists
C) Material Certifications
D) Approved Installation Drawings - answerA) Concrete Strength Results

Module 2. When reporting stressing results, the following information is necessary to
record:
A) Jack and gauge serial number
B) Elongation measurements and percentage deviation
C) Both A and B
D) Gauge Manufacturer
E) All three, A, B, and D - answerC) Both A and B

Module 2. When moving post-tension cables across the site, the use of _______ is
permitted.
A) Nylon slings, with unloading as close as placement as possible
B) Smooth finished chains with limited use
C) Epoxy coated high strength wire with limited use
D) A large front loader exercising caution - answerNylon slings, with unloading as close
to the placement as possible

Module 2. When storing post-tension cables, care must be taken to: - answerPrevent
the cables from being exposed to weather elements and moisture

Module 2. During deliver, it is the ______________ responsibility to ensure the
delivered items match the shipping list. - answerBuyer's

Module 2. According to the Field Procedures Manual for Unbonded Single Strand
Tendons, the follow documents must be kept on site: - answer1) Approved Installation
Drawings
2) Shipping Lists
3) Material Certifications
4) Jack Calibrations
5) Stressing Records

Module 2. Install drawings show: - answerPlan views, elevation views, and details so
the subcontractor and inspector can clearly see the tendon layout. This includes tendon
profiles, also known as drape.

Module 2. Drape - answerTendon profiles

Module 2. Material Certifications - answerDocuments that describe the cables' physical
properties and factory testing results.

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
julianah420 Phoenix University
View profile
Follow You need to be logged in order to follow users or courses
Sold
654
Member since
2 year
Number of followers
323
Documents
33793
Last sold
16 hours ago
NURSING,TESTBANKS,ASSIGNMENT,AQA AND ALL REVISION MATERIALS

On this page, you find all documents, package deals, and flashcards offered by seller julianah420

4.3

149 reviews

5
101
4
20
3
8
2
5
1
15

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions