NCCER MODULE 44105 EXAM
CONSTRUCTION DOCUMENTS
QUESTIONS WITH COMPLETE
ANSWERS
1. All change orders must be _______.
a) within the intent of the contract
b) logged daily
c) initiated by the project manager
d) updated weekly - Answer-a) within the intent of the contract
2. The type of insurance policy that provides coverage against the loss or damage of
company- owned or leased equipment not covered under a builder's risk policy is called
a(n).
a) general liability policy
b) workmen's tools compensation policy
c) equipment floater policy
d) production equipment liability policy - Answer-c) equipment floater policy
3. To request payment, the contractor prepares ______.
a) an invoice
b) certifications and representations
c) a consent of surety
d) a schedule of value - Answer-d) a schedule of value
4. Two of the most important project close-out documents are _____.
a) operation and maintenance manuals
b) certificate of occupancy and record drawings
c) consent of surety and release of liens
d) warranties and guarantees - Answer-c) consent of surety and release of liens
5. Which of these types of contracts is a variation of the fixed-price and cost-plus
contracts?
a) Unit-cost contract
b) Fast-tracking contract
c) Target contract
d) Subcontract - Answer-c) Target contract
6. The certificate of occupancy for a facility is issued by the ______.
a) construction management firm
b) general contractor's legal team
c) both the architect and engineer
CONSTRUCTION DOCUMENTS
QUESTIONS WITH COMPLETE
ANSWERS
1. All change orders must be _______.
a) within the intent of the contract
b) logged daily
c) initiated by the project manager
d) updated weekly - Answer-a) within the intent of the contract
2. The type of insurance policy that provides coverage against the loss or damage of
company- owned or leased equipment not covered under a builder's risk policy is called
a(n).
a) general liability policy
b) workmen's tools compensation policy
c) equipment floater policy
d) production equipment liability policy - Answer-c) equipment floater policy
3. To request payment, the contractor prepares ______.
a) an invoice
b) certifications and representations
c) a consent of surety
d) a schedule of value - Answer-d) a schedule of value
4. Two of the most important project close-out documents are _____.
a) operation and maintenance manuals
b) certificate of occupancy and record drawings
c) consent of surety and release of liens
d) warranties and guarantees - Answer-c) consent of surety and release of liens
5. Which of these types of contracts is a variation of the fixed-price and cost-plus
contracts?
a) Unit-cost contract
b) Fast-tracking contract
c) Target contract
d) Subcontract - Answer-c) Target contract
6. The certificate of occupancy for a facility is issued by the ______.
a) construction management firm
b) general contractor's legal team
c) both the architect and engineer