ICC Soils Certification Exam Questions with all Correct Answers A P.I that is greater than 15 is considered as what? - ANSWER-a material that has expansive potential .according to the IBC, what is the contractor responsible for? - ANSWER-coordinating with special inspectors, the building official, and the RDP schedules the preconstruction meeting coordinates the on-site special inspection activities .at the end of a project the special inspector should - ANSWER-submit a final report .at the end of a project, who should the special inspector submit the final report to? what shall it state? - ANSWER-the building department stating that all items requiring special inspection and testing by the statement of special inspections are in conformance with the approved plans and specifications .at the job site the special inspector should - ANSWER-Notify contractor personnel of the presence and responsibilities at the job site follow site requirements for safety and sign in observe the assigned work perform or observe required testing report on nonconforming items immediately ( any discrepancies) provide timely progress reports ( on a daily or weekly basis determined by the building official) .before an observation is complete what should the special inspector record? - ANSWER-each location of inspection type of inspection frequency of inspection note any nonconforming items on the discrepancies report and give it to the contractor document any changes , requests for information (RFI) or email corrections to the construction process .Clayey gravels; poorly graded gravel-and-clay mixes - ANSWER-GC .Clayey sands; poorly graded sand-clay mixes - ANSWER-SC .do all excavations including trenches that are less the 5 feet deep need to be examined by a special inspector? - ANSWER-absolutely yes .during fabrication who will review the quality control documentation and alert the manufacturer to any discrepancies? - ANSWER-The special inspector .for compaction, when water content increases what happens to the dry density - ANSWER-it will become denser until a certain point is reached , at which point the density will begin to decrease. .for concrete construction when is special inspection required? - ANSWER-replacement placing and post placement inspections compared concrete to document requirements collects concrete samples to be tested for strength verifies temp and moisture requirements are met .for gravelly soils or crushed stone how thick of lifts should be placed? - ANSWER-10 to 12 inches , compacting to about 8 inches .for progress reports, when should the special inspector complete them? - ANSWER-on a timely basis as determined by the building official .foundation grades and drainage must dos - ANSWER-surface water must be directed away from the foundation area and not be permitted to stand within or adjacent to the work

Show more Read less
Institution
ICC Soils Certification
Course
ICC Soils Certification









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
ICC Soils Certification
Course
ICC Soils Certification

Document information

Uploaded on
August 21, 2024
Number of pages
15
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Content preview

ICC Soils Certification Exam Questions
with all Correct Answers
A P.I that is greater than 15 is considered as what? - ANSWER-a material that has
expansive potential

.according to the IBC, what is the contractor responsible for? - ANSWER-coordinating
with special inspectors, the building official, and the RDP

schedules the preconstruction meeting

coordinates the on-site special inspection activities

.at the end of a project the special inspector should - ANSWER-submit a final report

.at the end of a project, who should the special inspector submit the final report to? what
shall it state? - ANSWER-the building department stating that all items requiring special
inspection and testing by the statement of special inspections are in conformance with
the approved plans and specifications

.at the job site the special inspector should - ANSWER-Notify contractor personnel of
the presence and responsibilities at the job site

follow site requirements for safety and sign in

observe the assigned work

perform or observe required testing

report on nonconforming items immediately ( any discrepancies)

provide timely progress reports ( on a daily or weekly basis determined by the building
official)

.before an observation is complete what should the special inspector record? -
ANSWER-each location of inspection

type of inspection

frequency of inspection

note any nonconforming items on the discrepancies report and give it to the contractor

document any changes , requests for information (RFI) or email corrections to the
construction process

, .Clayey gravels; poorly graded gravel-and-clay mixes - ANSWER-GC

.Clayey sands; poorly graded sand-clay mixes - ANSWER-SC

.do all excavations including trenches that are less the 5 feet deep need to be examined
by a special inspector? - ANSWER-absolutely yes

.during fabrication who will review the quality control documentation and alert the
manufacturer to any discrepancies? - ANSWER-The special inspector

.for compaction, when water content increases what happens to the dry density -
ANSWER-it will become denser until a certain point is reached , at which point the
density will begin to decrease.

.for concrete construction when is special inspection required? - ANSWER-replacement
placing and post placement inspections
compared concrete to document requirements
collects concrete samples to be tested for strength
verifies temp and moisture requirements are met

.for gravelly soils or crushed stone how thick of lifts should be placed? - ANSWER-10 to
12 inches , compacting to about 8 inches

.for progress reports, when should the special inspector complete them? - ANSWER-on
a timely basis as determined by the building official

.foundation grades and drainage must dos - ANSWER-surface water must be directed
away from the foundation area and not be permitted to stand within or adjacent to the
work

foundations must have and adequate concrete reveal of 4 to 8 inches before the top of
the soil is encountered

areas around the foundation must slope away to a swale or drainage pipe system that
will drain adequately off site

slopes should have approximately 6- inch fall within 10 feet from building on all sides for
all buildings, including residence

.foundation red lights - ANSWER-design not in accordance with geotechnical
recommendations

foundation location differs from site investigation location

foundation plans not adequate or complete

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TopGradeGuides Harvard University
View profile
Follow You need to be logged in order to follow users or courses
Sold
22
Member since
1 year
Number of followers
11
Documents
1655
Last sold
23 hours ago
TOP SELLER CENTER

EXCELLENT HOMEWORK HELP AND TUTORING ,ALL KIND OF QUIZ AND EXAMS WITH GUARANTEE OF A EXCELLENT HOMEWORK HELP AND TUTORING ,ALL KIND OF QUIZ AND EXAMS WITH GUARANTEE OF A Am an expert on major courses especially; psychology,Nursing, Human resource Management and Mathemtics Assisting students with quality work is my first priority. I ensure scholarly standards in my documents and that\'s why i\'m one of the BEST GOLD RATED TUTORS in STUVIA. I assure a GOOD GRADE if you will use my work.

Read more Read less
2.3

3 reviews

5
0
4
1
3
0
2
1
1
1

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions