BPI Standards for the Building Analyst Professional Exam | Questions & Answers (100
%Score) Latest Updated 2024/2025 Comprehensive Questions A+ Graded Answers | With
Expert Solutions
All technicians must have necessary safety equipment required by OSHA and proper training - - fitted
respirator (with canister filters)
- dust masks
- gloves
- protective clothing
- safety glasses
- hard hats (as required)
A copy of the MSDS (materials safety data sheets) for ALL materials used on the job - - must be kept on
the crew vehicle
- available to all crew members
In the presence of asbestos, lead, mold, and/or other potentially hazardous material (is known or
suspected), ALL relevant state and federal (EPA) guidelines must be followed - **Blower door
depressurization tests may NOT be performed in homes where there is a risk of asbestos becoming
airborne and being drawn into the dwelling
Respirators MUST be worn when: - working in areas where exposure to airborne mold, asbestos, lead,
fiberglass, or formaldehyde is a risk
CO levels in the ambient air around the technician must be monitored throughout ALL combustion
safety tests. - Must abort if CO concentrations greater than 35 ppm are recorded.
**CO producing appliances must be disable and repaired before proceeding with additional diagnostics
or inspections.
MINIMUM Health & Safety Requirement (Buidling Analyst Professional) - These requirements apply to
all jobs with work related to energy efficiency and/or IAQ performed by BPI accredited firms.
, When air sealing, enclosed cavity insulation representing 15% or more of the total building shell area,
OR sealing of the ducts outside the thermal envelope are recommended... - the work scope MUST
include pre and post-installation blower door tests
Whenever blower door tests are required: - the results MUST be compared to the Building Airflow
Standard (BAS) to verify compliance with ASHRAE 62-89 (62-2 after Feb. 1st) requirements for
ventilation.
If natural ventilation is inadequate according to the ASHRAE standard, mechanical ventilation MUST be
installed OR recommended as part of the work scope to increase the ventilation to required levels (refer
to page 6)
A preliminary and post-installation safety inspection of all combustion appliances MUST be completed
whenever... - changes to the building envelope and/or heating system are part of the work scope
The combustion appliance and safety inspection includes all of the following: - - carbon monoxide test
- draft measurement
- spillage evaluation
- worse-case depressurization of the CAZ
In homes with natural gas/propane service... - the gas line must be inspected thoroughly AND all leaks
repaired (tagged for repair)
Combustion safety test results must be acted upon appropriately according to: - the Combustion Safety
Action Level Table
- pg. 13 (standards)
Whenever an appliance fails any of the combustion safety test - appropriate repairs MUST be completed
OR specified in the work scope according to the requirements listed
-pg. 13 (standards)
%Score) Latest Updated 2024/2025 Comprehensive Questions A+ Graded Answers | With
Expert Solutions
All technicians must have necessary safety equipment required by OSHA and proper training - - fitted
respirator (with canister filters)
- dust masks
- gloves
- protective clothing
- safety glasses
- hard hats (as required)
A copy of the MSDS (materials safety data sheets) for ALL materials used on the job - - must be kept on
the crew vehicle
- available to all crew members
In the presence of asbestos, lead, mold, and/or other potentially hazardous material (is known or
suspected), ALL relevant state and federal (EPA) guidelines must be followed - **Blower door
depressurization tests may NOT be performed in homes where there is a risk of asbestos becoming
airborne and being drawn into the dwelling
Respirators MUST be worn when: - working in areas where exposure to airborne mold, asbestos, lead,
fiberglass, or formaldehyde is a risk
CO levels in the ambient air around the technician must be monitored throughout ALL combustion
safety tests. - Must abort if CO concentrations greater than 35 ppm are recorded.
**CO producing appliances must be disable and repaired before proceeding with additional diagnostics
or inspections.
MINIMUM Health & Safety Requirement (Buidling Analyst Professional) - These requirements apply to
all jobs with work related to energy efficiency and/or IAQ performed by BPI accredited firms.
, When air sealing, enclosed cavity insulation representing 15% or more of the total building shell area,
OR sealing of the ducts outside the thermal envelope are recommended... - the work scope MUST
include pre and post-installation blower door tests
Whenever blower door tests are required: - the results MUST be compared to the Building Airflow
Standard (BAS) to verify compliance with ASHRAE 62-89 (62-2 after Feb. 1st) requirements for
ventilation.
If natural ventilation is inadequate according to the ASHRAE standard, mechanical ventilation MUST be
installed OR recommended as part of the work scope to increase the ventilation to required levels (refer
to page 6)
A preliminary and post-installation safety inspection of all combustion appliances MUST be completed
whenever... - changes to the building envelope and/or heating system are part of the work scope
The combustion appliance and safety inspection includes all of the following: - - carbon monoxide test
- draft measurement
- spillage evaluation
- worse-case depressurization of the CAZ
In homes with natural gas/propane service... - the gas line must be inspected thoroughly AND all leaks
repaired (tagged for repair)
Combustion safety test results must be acted upon appropriately according to: - the Combustion Safety
Action Level Table
- pg. 13 (standards)
Whenever an appliance fails any of the combustion safety test - appropriate repairs MUST be completed
OR specified in the work scope according to the requirements listed
-pg. 13 (standards)