100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.6 TrustPilot
logo-home
Exam (elaborations)

PRM3701 - ASSESSMENT 2 - QUESTIONS AND ANSWERS - SEMESTER 2 - 2024

Rating
-
Sold
1
Pages
27
Grade
B
Uploaded on
21-06-2024
Written in
2023/2024

All assessments in this document scored distinctions. Using it correctly guarantees distinction

Institution
Course









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Course

Document information

Uploaded on
June 21, 2024
Number of pages
27
Written in
2023/2024
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

2024 – S1 – PRM3701 – ASSESSMENT 2 – Q&A



Assessment 2
Started on Wednesday, 13 March 2024,
State Finished
Completed on Wednesday, 13 March 2024,
Time taken
Marks 21/21.00
Grade 100.00 out of 100.00


Question 1
The integration of the lowest level of the WBS with the organizational units
responsible for performing the work is known as

a.
responsibility matrix.

b.
organization breakdown structure.

c.
work breakdown structure.

d.
priority matrix.

e.
process breakdown structure.

Feedback
Your answer is correct.

In practice, the outcome of this process is the organization breakdown structure
(OBS). The OBS depicts how the firm has organized to discharge work
responsibility. LO04-05



Question 2
You have just been given a project that has a specific completion date. After a
discussion with top management you find that while the date is important the cost is

1

, 2024 – S1 – PRM3701 – ASSESSMENT 2 – Q&A


more important and a slip in delivery would be acceptable if required to meet the cost
targets. The completion date is best classified as

a.
constrained.

b.
reduced.

c.
accepted.

d.
limited.

e.
optional.

Feedback
Your answer is correct.

For which criterion is it tolerable or acceptable not to meet the original parameters?
When trade-offs have to be made, is it permissible for the schedule to slip, to reduce
the scope and performance of the project, or to go over budget? In this incident cost
is constrained and the date will be accepted. LO04-03



Question 3
Below are ways the Work Breakdown Structure (WBS) helps in managing projects.
Which way listed below is incorrect

a.
with cost and time estimates the WBS makes it possible to plan, schedule and
budget the project.

b.
it provides management with information appropriate to each level.

c.
can be used to define communication channels.

d.

2

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
sotholesothole0 Myself
Follow You need to be logged in order to follow users or courses
Sold
167
Member since
2 year
Number of followers
84
Documents
208
Last sold
6 months ago

4.1

14 reviews

5
7
4
2
3
4
2
1
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions