BICSI - RTPM Study Set- Questions and Answers 100% Solved
BICSI - RTPM Study Set- Questions and Answers 100% Solved What two distinct processes does a Telecommunications Project Management (TPM) consist of? Design, and Implementation/ Installation Typical Design PM Responsibilities: -Review expression of interest for client. -Perform a user needs analysis. -Perform site surveys and meet with client. -Generate preliminary design submittals. -Respond to/incorporate client comments. -Prepare final bid documents/RFP and engineer's cost estimate. -Issue final RFP package to client. -Client makes RFP available to potential bidders