NASCLA PRACTICE EXAM 9 Questions With 100% Correct Answers
NASCLA PRACTICE EXAM 9 Questions With 100% Correct Answers 3 main reasons contract changes occur - answerscope of work, condition unforeseen, change design Crashing - answerthe process of accelerating a project Quantity Takeoff - answerThe foundation of a construction estimate Project Closeout - answerPrimary purpose of the closeout is to formalize project completion and disseminate information to project participants. Bid documents include - answerBidding documents, contract forms, conditions of the contract, specifications, drawings, addenda lump sum, unit price, cost plus - answer3 major types of contracts Design-Bid-Build, design build, construction management - answer3 most common delivery method 10% - answerA general contractor typically marks up the subcontractors's work Bid bonds/surety bonds - answerto ensure that the successful bidder will accept the contract once awarded Local Statutes or ordinances or bylaws - answerCan have a critical impact on all construction projects Accepted offer - answerNo contract is formed unless the receiving party has an offer - answerdoes not usually need to be made in writing or form partnering technique - answera process in which a culture of cooperation and open communication is encourage through workshops and other exercises facilitated by organizational development professionals. Certificate of Substantial Completion - answerProject close out officially begins when the contractor turns over _
École, étude et sujet
- Établissement
- NASCLA
- Cours
- NASCLA
Infos sur le Document
- Publié le
- 6 mars 2024
- Nombre de pages
- 5
- Écrit en
- 2023/2024
- Type
- Examen
- Contient
- Questions et réponses
Sujets
-
nascla practice exam 9 questions with 100 correct
Document également disponible en groupe