The documents cover the exam (chapter 6) of Lean Six Sigma GreenBelt of the Minor Supply Chain Management.

Instelling
Vak









Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Gekoppeld boek

Geschreven voor

Instelling
Studie
Vak

Documentinformatie

Geüpload op
16 februari 2024
Aantal pagina's
8
Geschreven in
2023/2024
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

1h30p

QUESTION 1

During which phase of DMAIC is a SIPOC usually applied according to Theisens?
A Impro
ve
b Contr
ol
c Analy
sis
D Defin
e


QUESTION 2
1. In the context of lean, the company plans to introduce self-managing teams. Given is an
assembly line with the following 5 operations and capacities per employee.
● Operation 1: 20 units per hour per employee

● Operation 2: 40 units per hour per employee

● Operation 3: 12 units per hour per employee

● Operation 4: 16 units per hour per employee

● Operation 5: 20 units per hour per employee
An LSS GB wants to apply line balancing to achieve maximum flow and resource efficiency.
Several employees (also part-time) can be deployed for one operation. It may also happen that
an employee performs multiple operations.
How many employees are at least needed in the self-managing team if the takt time is 2
minutes?
The basic principle is that every employee can perform all operations.
Round to the nearest whole number.
Total processing time
= (60/20) +(60/40) +(60/12) +(60/16) +(60/20)
=16,25 = sum of cycle time
Number of resource = Sum of cycle time/ Task time = 16,25/2 = 8
employee


10 points
QUESTION 3
1. At which station is the bottleneck?
Lathe
Robot
Assembly
Package

10 points
QUESTION 4
1. A factory works for 480 minutes every day (excluding maintenance and breakdowns). When
production planning, they take into account a downtime of 30 minutes per day due to
disruptions and planned maintenance. The machine runs for a total of 450 minutes.

, The factory produces three products with the following forecast average daily demand: 9 A's,
6 B's, and 3 C's. The processing time for each product is 15 minutes and the setup time for the
start of each batch is unknown. These are the same for all products A, B and C. So a new setup
is required to start each batch. You can assume that the batch of a product can be finished the
next day without any additional setup.

What is the setup time per batch in hours for an EPE of 4 days?




Capacity of machine (total available working time) = 450 minutes 20 points
Processing time a day for 3 products = 15*(9+6+3) = 270 min QUESTION 5
The remaining time = 450-270 = 180 m 1. It is stated
The set-up time for 4 products = EPE *Remaining time = 4 days * 180 = that when
720m
The set-up time for 1 product = 720/3=240m ====240/60 = 4 hours

manufacturing a toaster, 20 possible defects can occur per product. 2500 toasters were
produced. 50 defects were found during the inspections of the toasters.
Calculate DPU to two decimal places (e.g., 0.43). 0.02
DPU = Amount of Defects/ Number of Units
= 50/2500 = 0,02
10 points
QUESTION 6
1. A Sperta service technician receives electric bicycles from dealers every day that need to be
repaired. It is given that an electric bicycle can have 100 possible defects. The number of
opportunities is therefore 100 per product.
He discovered yesterday that 8 out of 10 bicycles had 1 or more faults. So 2 electric bicycles
were correct. A total of 20 defects were found.
Calculate the DPMO.
20,000 (use the comma)
DPMO = (Number of defects*1,000,000)/ (Opportunities*Number of Units)
Number of units = 10
10 points
QUESTION 7
1. Which of the following best describes the difference between ppm and DPMO?
DPMO assumes that each part/process can have only one defect possibility unlike ppm where
each unit can have multiple defects.
PPM considers the defective unit as a whole, while DPMO refers to multiple opportunities per
part / process.
Opportunite in the object and area
Ppm is determined by dividing the number of defective units by the number of non-defective
units.
DPMO ignores the number of "defective opportunities" per product, while ppm distinguishes
between products with many "defective opportunities" and those with few "defective
opportunities".

10 points
QUESTION 8
$6.11
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten

Maak kennis met de verkoper
Seller avatar
trangphan

Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
trangphan Saxion Hogeschool
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
2
Lid sinds
2 jaar
Aantal volgers
0
Documenten
47
Laatst verkocht
3 maanden geleden

0.0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen