NERC CIP v7 Standards and Requirements Test 2024.
NERC CIP v7 Standards and Requirements Test 2024. CIP-002-5.1 - ANSWER BES Cyber System Categorization CIP-002 R1 - ANSWER Each Responsible Entity shall implement a process that considers each of the following assets for purposes of parts 1.1 through 1.3: Control Centers and backup Control Centers, Transmission stations and substations, Generation resources, Systems and facilities critical to system restoration, including Blackstart Resources and Cranking Paths and initial switching requirements, Special Protection Systems that support the reliable operation of the Bulk Electric System; and For Distribution Providers CIP-002 R1.1 - ANSWER Identify each of the high impact BES Cyber Systems according to Attachment 1, Section 1, if any, at each asset; CIP-002 R1.2 - ANSWER Identify each of the medium impact BES Cyber Systems according to Attachment 1, Section 2, if any, at each asset; CIP-002 R1.3 - ANSWER Identify each asset that contains a low impact BES Cyber System according to Attachment 1, Section 3, if any (a discrete list of low impact BES Cyber Systems is not required). CIP-002 R2.1 - ANSWER Review the identifications in Requirement R1 and its parts (and update them if there are changes identified) at least once every 15 calendar months, even if it has no identified items in Requirement R1, CIP-002 R2.2 - ANSWER Have its CIP Senior Manager or delegate approve the identifications required by Requirement R1 at least once every 15 calendar months, even if it has no identified items in Requirement R1. CIP-003-7 - ANSWER Security Management Controls CIP-003 R1 - ANSWER Each Responsible Entity shall review and obtain CIP Senior Manager approval at least once every 15 calendar months for one or more documented cyber security policies that collectively address the following topics: CIP-003 R2 - ANSWER Each Responsible Entity with at least one asset identified in CIP-002 containing low impact BES Cyber Systems shall implement one or more documented cyber security plan(s) for its low impact BES Cyber Systems that include the sections in Attachment 1. CIP-003 R3 - ANSWER Each Responsible Entity shall identify a CIP Senior Manager by name and document any change within 30 calendar days of the change.
Document information
- Uploaded on
- January 14, 2024
- Number of pages
- 20
- Written in
- 2023/2024
- Type
- Exam (elaborations)
- Contains
- Questions & answers