QUESTIONS WITH 100% CORRECT
ANSWERS
How is the default timescale in Microsoft Project 2016 arranged? - ANSWER By weeks and days.
What is the default view (screen) in Microsoft Project? - ANSWER The Gantt Chart view.
What criteria do you use when entering tasks in Microsoft Project? - ANSWER Enter them in
order of occurrence.
What is the default calendar in Microsoft Project? - ANSWER The Project calendar.
Which element of the triple constraint typically can't be changed for a surprise 50th-birthday-
party project? - ANSWER Time.
What occurs when you replace the Project Start Date selection in the Project Information dialog
box with the Project Finish Date? - ANSWER You can no longer change the start date.
What fields reflect default information in the Resource Sheet? - ANSWER Type, Initials,
Maximum Units, and Base Calendar.
What is the purpose of the Material Label column in the Resource Sheet? - ANSWER To describe
the quantity and unit of measure.
How do you assign resources using Microsoft Project? - ANSWER Use this path: Task name >
Resources tab > Assign Resources.
How can you find planned total project costs? - ANSWER Go to More Views > Task Sheet.