Klastoets 2 / Class Test 2 – 25 Sep 2013
30 minute, 25 punte / 30 minutes, 25 marks
Naam en Van / Name and surname ________________________
Studente nommer / Student Number: ________________________
Vraag 1 / Question 1
Gebruik die onderstaande koste tabel en netwerk diagram om die koste te bereken om projek TRY
te verkort met vyf weke. Wys al jou antwoorde week vir week. /
Use the cost table and network diagram below to calculate the cost to shorten project TRY by five
weeks. Show all your answers week by week.
A B C F
6 6 5 2
D E
7 6
Normaal / Normal Maximum Crashed
Aktiwiteit / Koste / Cost
Activity [per week] Tydsduur / Koste / Tydsduur / Koste /
Duration Cost Duration Cost
A 100 6 800 4 1 000
B 50 6 600 4 700
C 70 5 700 3 840
D 80 7 900 5 1 060
E 50 6 700 5 750
F - 2 500 2 500
Vul die antwoorde hieronder in / Fill the answers in below:
Aktiwiteit / Koste /
Week
Activity Cost
1
2
3
4
5
Totaal / Total
[11]