UNISA 2023 PRM3701-23-S2 Assessments Assessment 3
QUIZ
Information
Use the information below to construct a project network using the activity-on-
node (AON) method in order to answer questions that follow.
Activity ID Predecessor Duration (in days)
A None 3
B A 1
C A 4
D B 1
E B, C 2
F E 8
G D 2
H E 3
I F, G, H 1
J I 1
Question 1
Not yet answered
Marked out of 1.00
What is the earliest start (ES) time for activity I?
a. 7
b. 17
c. 12
d. 15
e. 9