DBIA - Project Delivery Exam Questions
with Solutions.
The existing federal law that required federal projects exceeding 100k to
require both a performance and a payment bond. Created a legal
separation between construction & Design - Correct Answer Miller Act
What are 3 fundamental decisions an Owner must make when initiating
a feasible project? - Correct Answer Delivery system, Type of
Procurement and Type of Contract Format.
What is the most common project delivery system? - Correct Answer
Design Bid Build (Low Bid)
In traditional DBB delivery, who does the architect sign their contract
with? - Correct Answer The Owner
What type of relationship does the contractor have with an architect in
Design Bid Build? - Correct Answer None
, DBIA - Project Delivery Exam Questions
with Solutions.
Why would you choose a Design Build delivery System? - Correct
Answer Scheduling Restraints or needs to be fast-tracked
If the owner wants to shift risk to one party, what project delivery
method would they choose? - Correct Answer Design Build
What type of project delivery best suits a complex project requiring
close coordination of design and construction expertise? - Correct
Answer Design Build
What are some forms of Design Build entities? - Correct Answer 1 -
Joint Venture
2 - Integrated DB Firm
3- A/E Led
4 - Contractor Led
Does the Owner bear risk in a design-bid-build? - Correct Answer Yes
with Solutions.
The existing federal law that required federal projects exceeding 100k to
require both a performance and a payment bond. Created a legal
separation between construction & Design - Correct Answer Miller Act
What are 3 fundamental decisions an Owner must make when initiating
a feasible project? - Correct Answer Delivery system, Type of
Procurement and Type of Contract Format.
What is the most common project delivery system? - Correct Answer
Design Bid Build (Low Bid)
In traditional DBB delivery, who does the architect sign their contract
with? - Correct Answer The Owner
What type of relationship does the contractor have with an architect in
Design Bid Build? - Correct Answer None
, DBIA - Project Delivery Exam Questions
with Solutions.
Why would you choose a Design Build delivery System? - Correct
Answer Scheduling Restraints or needs to be fast-tracked
If the owner wants to shift risk to one party, what project delivery
method would they choose? - Correct Answer Design Build
What type of project delivery best suits a complex project requiring
close coordination of design and construction expertise? - Correct
Answer Design Build
What are some forms of Design Build entities? - Correct Answer 1 -
Joint Venture
2 - Integrated DB Firm
3- A/E Led
4 - Contractor Led
Does the Owner bear risk in a design-bid-build? - Correct Answer Yes