WGU C483 Practice Test Questions With 100% Verified Answers
1.)The planning level with the shortest time horizon is known as _____ planning. A)operational B)tactical C)managerial D)developmental E)vertical - ️️A 2.)The planning process is similar to the _____ process in that both have a series of steps that are typically repeated in a cycle. A)strategy-mapping B)tactical alignment C)goal-setting D)decision-making E)environmental analysis - ️️D 3.)In a SWOT analysis, the absence of reliable suppliers would be considered as a(n): A)weakness and a threat. B)weakness. C)strength. D)opportunity. E)threat. - ️️B