Post-Test with complete solution
Anticipate and manage risk by planning.
The statement, "You are more likely to control risks when they are identified earlier
rather than later" is associated with what level of Risk Management principle?
Accept risk when benefits outweigh the cost.
Weighing risks against benefits and value is an example of applying which of the
following Risk Management principles?
Determining the probability and severity of a DUI caused accident before going to
a bar.
Which of the following is an example of the second step, assess hazards, in the 5-step
Risk Management Process.
Identify hazards, assess hazards, make decisions, implement controls, supervise.
Which of the following depicts the 5-step Risk Management Process in the correct
order?
Deliberate
A battalion commander and her staff conduct a Marine Corps Planning Process (MCPP)
session to develop an operations order (OPORD) for an upcoming offensive operation.
The operation begins in 96-hours. The MCPP session would fall under which Risk
Management level?
False
True or false, creating a risk assessment worksheet is associated with Time Critical
Risk Management (TCRM).
Balance your resources.
Your unit is on a security patrol during a stability operation. You come across a civilian
female who is in great distress. The Corpsman assesses that she is pregnant, in labor,
and about to deliver. There are no indications of enemy activity in the local area. Under
the rules of engagement (ROE), your patrol is required to provide medical assistance to
civilians when there are no imminent threats. Using the ABCD Model what would be the
next step?
Administrative
First Sergeant Jones posts a sign outside the entrance to the maintenance shop
indicating that hearing protection is required inside. This is an example of what type of
risk control?
Designing and installing a ventilation system to reduce exposure to toxic fumes
in a building.
Choose an example of an engineering control.
Operator level.
After a mishap, which level will investigators normally first address during root cause
analysis?
Accept no unnecessary risk.
Which Risk Management principle is best demonstrated by thorough hazard
identification and assessment in order to prevent needlessly jeopardizing Marines and
equipment?