100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

PMI (PMP) Exam 6th Edition PMBOK. TEST BANK Questions with answers/ 2022/2023 updates.

Rating
-
Sold
-
Pages
347
Grade
A+
Uploaded on
17-10-2022
Written in
2022/2023

PMI (PMP) Exam 6th Edition PMBOK. Questions with answers/ 2022/2023 updates. An element of the project scope statement is: A. Acceptance criteria. B. A stakeholder list. C. A summary budget. D. High-level risks. - A Reserves Analysis - Risk management method of determining contingency or management reserves for schedule Which document describes the necessary information to determine if a project is worth the required investment? A. Cost baseline B. Service level agreement C. Memorandum of understanding D. Business case - D Which input to the Plan Risk Management process provides information on high-level risks? A. Project charter B. Enterprise environmental factors C. Stakeholder register D. Organizational process assets - A Which item is an example of personnel assessment? A. Resource calendar B. Tight matrix C. Team-building activity D. Focus group - D Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project? A. Feedback analysis B. Stakeholder analysis C. Communication management plan D. Stakeholder management plan - D Which input to the Identify Stakeholders process provides information about internal or external parties related to the project? A. Procurement documents B. Communications plan C. Project charter D. Stakeholder register - C The Identify Stakeholders process is found in which Process Group? A. Initiating B. Monitoring and Controlling C. Planning D. Executing - A An input to Develop Project Charter is a/an: A. Business case. B. Activity list. C. Project management plan. D. Cost forecast. - A Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project? A. Project Risk Management B. Project Human Resource Management C. Project Scope Management D. Project Stakeholder Management - D Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements? A. Stakeholder register B. Scope management plan C. Stakeholder management plan D. Project charter - A In which Knowledge Area is the project charter developed? A. Project Cost Management B. Project Scope Management C. Project Time Management D. Project Integration Management - D The ability to influence cost is greatest during which stages of the project? A. Early B. Middle C. Late D. Completion - A Which process involves developing an approximation of the monetary resources needed to complete project activities? A. Estimate Costs B. Control Costs C. Determine Budget D. Plan Cost Management - A Which tool or technique is used in the Develop Project Management Plan process? A. Pareto diagram B. Performance reporting C. SWOT analysis D. Expert judgment - D The organization's perceived balance between risk taking and risk avoidance is reflected in the risk: A. Responses B. Appetite C. Tolerance D. Attitude - A An output of the Manage Stakeholder Engagement process is: A. change requests B. enterprise environmental factors C. the stakeholder management plan D. the change log - A Which process numerically analyzes the effect of identified risks on overall project objectives? A. Plan Risk Management B. Plan Risk Responses C. Perform Quantitative Risk Analysis D. Perform Qualitative Risk Analysis - C Which Collect Requirements output links the product requirements to the deliverable that satisfy them? A. Requirements documentation B. Requirements traceability matrix C. Project management plan updates D. Project documents updates - B A temporary endeavor that creates a unique product or service is called a: A. Project B. Plan C. Program D. Portfolio - A The process of prioritizing risks for further analysis or action is known as: A. Plan Risk Management. B. Plan Risk Responses. C. Perform Qualitative Risk Analysis. D. Perform Quantitative Risk Analysis. - C Stakeholder satisfaction should be managed as a key project: A. Benefit B. Initiative C. Objective D. Process - C Which cost is associated with nonconformance? A. Liabilities B. Inspections C. Training D. Equipment - A Identify Risks is part of which Process Group? A. Planning B. Executing C. Closing D. Initiating - A The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the: A. Project management plan. B. Project charter. C. Work breakdown structure. D. Stakeholder register. - B Which Process Group and Knowledge Area include the Sequence Activities process? A. Executing Process Group and Project Time Management B. Executing Process Group and Project Cost Management C. Planning Process Group and Project Time Management D. Planning Process Group and Project Cost Management - C In the Plan Stakeholder Management process, expert judgment is used to: A. Provide information needed to plan appropriate ways to engage project stakeholders. B. Ensure comprehensive identification and listing of new stakeholders. C. Analyze the information needed to develop the project scope statement. D. Decide the level of engagement of the stakeholders at each required stage. - D Power, urgency, and legitimacy are attributes of which stakeholder classification model? A. Salience B. Influence/impact C. Power/interest D. Power/influence - A Through whom do project managers accomplish work? A. Consultants and stakeholders B. Stakeholders and functional managers C. Project team members and consultants D. Project team members and stakeholders - D A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process? A. Plan Stakeholder Management B. Identify Stakeholders C. Manage Stakeholder Engagement D. Control Stakeholder Engagement - A Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as: A. organizational skills B. technical skills C. communication skills D. hard skills - C When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an: A. improvement B. program C. result D. portfolio - A The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk: A. management B. response C. tolerance D. appetite - D The zero duration of milestones in project planning occurs because milestones: A. Are unpredictable and challenge the Plan Schedule Management process. B. Occur at random times in the project plans. C. Represent a moment in time such as a significant project point or event. D. Represent both significant and insignificant points in the project and are difficult to anticipate. - C The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as: A. recognition and rewards B. compliance C. staff acquisition D. training needs - D Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be: A. Continuous B. Discrete C. Regulated D. Arbitrary - A In project management, a temporary project can be: A. Completed without planning B. A routine business process C. Long in duration D. Ongoing to produce goods - C Which document in the project management plan can be updated in the Plan Procurement Management process? A. Budget estimates B. Risk matrix C. Requirements documentation D. Procurement documents - C Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree? A. Uniform B. Continuous C. Discrete D. Linear - C Which stakeholder approves a project's result? A. Customer B. Sponsor C. Seller D. Functional manager - A Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives? A. Collect Requirements B. Plan Scope Management C. Define Scope D. Define Activities - A Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and: A. Available organizational assets B. Project staff assignments C. Interpersonal skills D. Enterprise environmental factors - A What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)? A. 0.03 B. 0.06 C. 0.10 D. 0.50 - B A complete set of concepts, terms, and activities that make up an area of specialization is known as: A. a Knowledge Area B. a Process Group C. program management D. portfolio management - A The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as: A. exploit B. avoid C. mitigate D. share - C Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager? A. Control Quality B. Monitor and Control Project Work C. Control Scope D. Perform Integrated Change Control - D Project management processes ensure the: A. alignment with organizational strategy B. efficient means to achieve the project objectives C. performance of the project team D. effective flow of the project throughout its life cycle - D Which project risk listed in the table below is most likely to occur? RISK PROBABILITY IMPACT 1 L M 2 H H 3 L L 4 M L A. 1 B. 2 C. 3 D. 4 - B Which is an enterprise environmental factor? A. Marketplace conditions B. Policies and procedures C. Project files from previous projects D. Lessons learned from previous projects - A Project Stakeholder Management focuses on: A. project staff assignments B. project tea m acquisition C. managing conflicting interests D. communication methods - C A risk that arises as a direct result of implementing a risk response is called a: A. contingent risk B. residual risk C. potential risk D. secondary risk - D The purpose of developing a project scope management plan is to: A. Manage the timely completion of the project. B. Ensure that the project includes all of the work required. C. Make sure the project will satisfy the needs for which it was begun. D. Reduce the risk of negative events in the project. - B A tool and technique used in the Develop Project Charter process is

Show more Read less
Institution
Course











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Course

Document information

Uploaded on
October 17, 2022
Number of pages
347
Written in
2022/2023
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

PMI (PMP) Exam 6th Edition PMBOK.
Questions with answers/ 2022/2023
updates.


An element of the project scope statement is:



A. Acceptance criteria.

B. A stakeholder list.

C. A summary budget.

D. High-level risks. - ✔✔A



Reserves Analysis - ✔✔Risk management method of determining contingency or management reserves
for schedule



Which document describes the necessary information to determine if a project is worth the required
investment?



A. Cost baseline

B. Service level agreement

C. Memorandum of understanding

D. Business case - ✔✔D



Which input to the Plan Risk Management process provides information on high-level risks?



A. Project charter

B. Enterprise environmental factors

C. Stakeholder register

,D. Organizational process assets - ✔✔A



Which item is an example of personnel assessment?



A. Resource calendar

B. Tight matrix

C. Team-building activity

D. Focus group - ✔✔D



Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders
can best be involved in a project?



A. Feedback analysis

B. Stakeholder analysis

C. Communication management plan

D. Stakeholder management plan - ✔✔D



Which input to the Identify Stakeholders process provides information about internal or external parties
related to the project?



A. Procurement documents

B. Communications plan

C. Project charter

D. Stakeholder register - ✔✔C



The Identify Stakeholders process is found in which Process Group?



A. Initiating

B. Monitoring and Controlling

,C. Planning

D. Executing - ✔✔A



An input to Develop Project Charter is a/an:



A. Business case.

B. Activity list.

C. Project management plan.

D. Cost forecast. - ✔✔A



Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted
by or impact a project?



A. Project Risk Management

B. Project Human Resource Management

C. Project Scope Management

D. Project Stakeholder Management - ✔✔D



Which input to Collect Requirements is used to identify stakeholders who can provide information on
requirements?



A. Stakeholder register

B. Scope management plan

C. Stakeholder management plan

D. Project charter - ✔✔A



In which Knowledge Area is the project charter developed?



A. Project Cost Management

, B. Project Scope Management

C. Project Time Management

D. Project Integration Management - ✔✔D



The ability to influence cost is greatest during which stages of the project?



A. Early

B. Middle

C. Late

D. Completion - ✔✔A



Which process involves developing an approximation of the monetary resources needed to complete
project activities?



A. Estimate Costs

B. Control Costs

C. Determine Budget

D. Plan Cost Management - ✔✔A



Which tool or technique is used in the Develop Project Management Plan process?



A. Pareto diagram

B. Performance reporting

C. SWOT analysis

D. Expert judgment - ✔✔D



The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:

A. Responses

B. Appetite
$14.99
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached


Also available in package deal

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
QuickPass Chamberlain College Of Nursing
Follow You need to be logged in order to follow users or courses
Sold
410
Member since
3 year
Number of followers
304
Documents
6372
Last sold
1 month ago
Get all Documents you need at discount.

All nursing docs available: question banks, summaries, study guide and test banks

3.8

97 reviews

5
52
4
11
3
10
2
10
1
14

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions