Question 1
One of the deliverables in your project involves marketing
your new product with email blasts. Your team writes
several drafts of the different marketing materials,
generates an email list, and programs the emails to be
sent on the correct dates. Which of the following
represents a milestone in your project plan?
❖Marketing emails are sent on scheduled dates.
Question 2
,Page 2 of 310
One of the tasks in your project involves setting up the
stage for a talent show. Before the team can do this, you
need estimates from an audiovisual contractor, and the
construction crew needs to build the stage backdrop.
What term refers to these preliminary needs?
❖Task dependencies
❖Vendors
❖Milestones
You start a new job as a project manager in an industry
that is unfamiliar to you. Which of the following are
examples of domain knowledge that you will need to have
a basic understanding of? Select all that apply.
❖Industry terms
,Page 3 of 310
❖Industry processes
Question 5
You have gathered information from project
documentation and the project team. With this
information, you identified and created a list of tasks for
your project plan. What is the next step for completing
your project plan?
❖Identify the order in which tasks need to be
completed.
When populating your project plan with a set of tasks,
when is the best time to hold a group brainstorming
session with team members to help identify tasks?
❖After you review project documentation
, Page 4 of 310
❖After you research your project online
Which of the following may indicate a milestone for your
project?
❖A task that your stakeholders have the most interest
in.
❖A task that can be completed most quickly.
❖A task that your team is most excited about.
Question 7
What term refers to a time estimate that only takes into
account the actual time it takes to complete a task?
WGU C954 - INFORMATION TECHNOLOGY
MANAGEMENT EXAM | OBJECTIVE
ASSESSMENT*** QUESTIONS AND ANSWERS |
VERIFIED AND WELL DETAILED ANSWERS
|DOWNLOAD AND PASS | LATEST EXAM
UPDATE 2026/2027
Question 1
One of the deliverables in your project involves marketing
your new product with email blasts. Your team writes
several drafts of the different marketing materials,
generates an email list, and programs the emails to be
sent on the correct dates. Which of the following
represents a milestone in your project plan?
❖Marketing emails are sent on scheduled dates.
Question 2
,Page 2 of 310
One of the tasks in your project involves setting up the
stage for a talent show. Before the team can do this, you
need estimates from an audiovisual contractor, and the
construction crew needs to build the stage backdrop.
What term refers to these preliminary needs?
❖Task dependencies
❖Vendors
❖Milestones
You start a new job as a project manager in an industry
that is unfamiliar to you. Which of the following are
examples of domain knowledge that you will need to have
a basic understanding of? Select all that apply.
❖Industry terms
,Page 3 of 310
❖Industry processes
Question 5
You have gathered information from project
documentation and the project team. With this
information, you identified and created a list of tasks for
your project plan. What is the next step for completing
your project plan?
❖Identify the order in which tasks need to be
completed.
When populating your project plan with a set of tasks,
when is the best time to hold a group brainstorming
session with team members to help identify tasks?
❖After you review project documentation
, Page 4 of 310
❖After you research your project online
Which of the following may indicate a milestone for your
project?
❖A task that your stakeholders have the most interest
in.
❖A task that can be completed most quickly.
❖A task that your team is most excited about.
Question 7
What term refers to a time estimate that only takes into
account the actual time it takes to complete a task?