Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 71 pages
Exam (elaborations)

[CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (CAPM) EXAM] – EXAM-STYLE QUESTIONS AND ANSWERS | VERIFIED AND WELL DETAILED ANSWERS | PLUS RATIONALES | GUARANTEED PASS | 2026/27 LATEST UPDATE | EXAM PREP | STUDY GUIDE | PRACTICE TEST

Document preview thumbnail
Preview 4 out of 71 pages

[CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (CAPM) EXAM] – EXAM-STYLE QUESTIONS AND ANSWERS | VERIFIED AND WELL DETAILED ANSWERS | PLUS RATIONALES | GUARANTEED PASS | 2026/27 LATEST UPDATE | EXAM PREP | STUDY GUIDE | PRACTICE TEST

Content preview

[CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (CAPM) EXAM] – EXAM-STYLE
QUESTIONS AND ANSWERS | VERIFIED AND WELL DETAILED ANSWERS | PLUS
RATIONALES | GUARANTEED PASS | 2026/27 LATEST UPDATE | EXAM PREP |
STUDY GUIDE | PRACTICE TEST

1. A project manager is evaluating stakeholder engagement levels at the start
of a complex infrastructure project. The project sponsor has high authority and
high interest, while a regulatory agency has high authority and low interest.
According to the power/interest grid, which stakeholder engagement strategy
is most appropriate for the regulatory agency?

A. Manage closely
B. Keep satisfied
C. Monitor
D. Keep informed

Correct Answer: B. Keep satisfied

*Rationale: The power/interest grid categorizes stakeholders based on their
authority and interest. The regulatory agency, possessing high authority but low
interest, is best managed using a "Keep satisfied" strategy, as they can significantly
impact the project's success but do not require daily engagement. "Manage closely"
is for stakeholders with both high power and high interest. "Monitor" is for low
power, low interest stakeholders. "Keep informed" is for low power, high interest
stakeholders.




2. Which of the following represents the most accurate definition of the project
charter?

,A. A detailed plan that defines how the project will be executed, monitored, and
controlled.
B. A document that formally authorizes the project's existence and grants the
project manager authority.
C. A high-level budget that outlines the estimated costs of the project.
D. A schedule that establishes the major milestones and deliverables for the
project.

Correct Answer: B. A document that formally authorizes the project's existence
and grants the project manager authority.

*Rationale: The project charter is a formal, high-level document issued by the
project sponsor or initiator. Its primary purpose is to authorize the project and
provide the project manager with the authority to apply organizational resources to
project activities. Options A, C, and D are all elements of the project management
plan, which is created after the charter is approved.




3. A project manager is estimating activity durations for a software
development project. After consulting with the team, she estimates the most
likely time for a coding task is 10 days, the optimistic time is 6 days, and the
pessimistic time is 20 days. Using the Program Evaluation and Review
Technique (PERT), what is the expected duration for this task?

A. 10 days
B. 11 days
C. 12 days
D. 15 days

,Correct Answer: B. 11 days

Rationale: The PERT formula calculates expected duration as (Optimistic + 4Most
Likely + Pessimistic) / 6. Applying the figures: (6 + 410 + 20) / 6 = (6 + 40 + 20) / 6
= = 11 days. Options A, C, and D represent miscalculations of the formula.*




4. During the Define Activities process, a project manager decomposes work
packages into smaller, manageable components. What is the primary purpose
of this decomposition?

A. To create the project schedule.
B. To define the activities required to produce the project deliverables.
C. To allocate the project budget.
D. To identify the stakeholders for the project.

Correct Answer: B. To define the activities required to produce the project
deliverables.

*Rationale: The Define Activities process involves breaking down work packages
into activities that represent the effort needed to complete them. This enables the
project manager to plan, schedule, and execute the work effectively. Option A is a
subsequent process (Develop Schedule), C is related to cost management, and D is
related to stakeholder management.




5. A project has the following tasks and dependencies: Task A (5 days), Task B
(3 days) can start after Task A is complete, Task C (4 days) can start after Task A

, is complete, and Task D (6 days) can start after both Task B and Task C are
complete. What is the float (slack) for Task C?

A. 0 days
B. 1 day
C. 2 days
D. 3 days

Correct Answer: A. 0 days

*Rationale: The critical path is A-B-D (5+3+6=14 days) and A-C-D (5+4+6=15
days). Therefore, the critical path is A-C-D, with a duration of 15 days. Any task on
the critical path has zero float. Since Task C is on the critical path, its float is 0 days.
Task B has 1 day of float, making options B, C, and D incorrect.




6. In the context of project procurement management, what is the primary
purpose of a bidder conference?

A. To award the contract to the selected bidder.
B. To provide a platform for potential sellers to clarify proposal requirements.
C. To negotiate final contract terms and conditions.
D. To evaluate the technical capabilities of potential sellers.

Correct Answer: B. To provide a platform for potential sellers to clarify proposal
requirements.

*Rationale: A bidder conference, also known as a pre-proposal conference, is a
meeting held before the seller's final proposal submission. Its purpose is to ensure
that all potential sellers have a clear and common understanding of the

Document information

Uploaded on
August 4, 2026
Number of pages
71
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$22.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
PrepPulse1
4.0
(21)
Sold
280
Followers
6
Items
3688
Last sold
1 day ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions